Statistics of LT New Service connections (Non AG) Applications from 01-APR-2025
State Statistics of LT New Service connections (Non AG) Applications Report generated as on 28-Sep-2025 |
|||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|
Service | Infra Status | Area | Notified Timeline (Days) | Number Of Applications Received | Number Of Applications Approved | Maximum (Days) | Minimum (Days) | Mean (Days) | Mode (Days) | Median (Days) | Compliance |
Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Metro | 3 | 59169 | 58029 | 148 | 0 | 11 | 9 | 8 | 98% |
Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 269833 | 259911 | 162 | 1 | 25 | 15 | 20 | 96% |
Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Urban | 7 | 48804 | 47403 | 159 | 0 | 21 | 8 | 14 | 97% |
Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Metro | 90 | 99315 | 85033 | 170 | 1 | 37 | 11 | 23 | 86% |
Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 57495 | 44447 | 167 | 11 | 65 | 161 | 78 | 77% |
Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Urban | 90 | 7749 | 6542 | 159 | 18 | 52 | 64 | 45 | 84% |
Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Metro | 3 | 1196 | 1061 | 111 | 13 | 14 | 13 | 14 | 89% |
Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 3076 | 2755 | 125 | 30 | 32 | 30 | 30 | 90% |
Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Urban | 7 | 827 | 733 | 124 | 0 | 16 | 1 | 5 | 89% |
Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Metro | 90 | 1185 | 940 | 144 | 18 | 43 | 18 | 19 | 79% |
Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 420 | 310 | 141 | 87 | 87 | 87 | 87 | 74% |
Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Urban | 90 | 116 | 88 | 69 | 2 | 20 | 6 | 14 | 76% |
Statistics of LT New Service connections (Non AG) Applications Report generated as on 28-Sep-2025 |
|||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Region | Zone | Circle | Division | Service | Infra Status | Area | Notified Timeline (Days) | Number Of Applications Received | Number Of Applications Approved | Maximum (Days) | Minimum (Days) | Mean (Days) | Mode (Days) | Median (Days) | Compliance |
CH. SAMBHAJINAGAR REGION | CH. SAMBHAJINAGAR ZONE | CH. SAMBHAJINAGAR (U) CIRCLE | CH. SAMBHAJINAGAR URBAN I DIVSION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Metro | 3 | 452 | 444 | 102 | 0 | 4 | 1 | 2 | 98% |
CH. SAMBHAJINAGAR REGION | CH. SAMBHAJINAGAR ZONE | CH. SAMBHAJINAGAR (U) CIRCLE | CH. SAMBHAJINAGAR URBAN I DIVSION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Metro | 90 | 3619 | 3357 | 126 | 0 | 8 | 2 | 5 | 93% |
CH. SAMBHAJINAGAR REGION | CH. SAMBHAJINAGAR ZONE | CH. SAMBHAJINAGAR (U) CIRCLE | CH. SAMBHAJINAGAR URBAN I DIVSION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Metro | 3 | 14 | 13 | 25 | 0 | 3 | 0 | 0 | 93% |
CH. SAMBHAJINAGAR REGION | CH. SAMBHAJINAGAR ZONE | CH. SAMBHAJINAGAR (U) CIRCLE | CH. SAMBHAJINAGAR URBAN I DIVSION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Metro | 90 | 38 | 26 | 33 | 0 | 7 | 0 | 4 | 68% |
CH. SAMBHAJINAGAR REGION | CH. SAMBHAJINAGAR ZONE | CH. SAMBHAJINAGAR (U) CIRCLE | CH. SAMBHAJINAGAR URBAN II.DIVSION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Urban | 7 | 934 | 927 | 107 | 0 | 8 | 1 | 5 | 99% |
CH. SAMBHAJINAGAR REGION | CH. SAMBHAJINAGAR ZONE | CH. SAMBHAJINAGAR (U) CIRCLE | CH. SAMBHAJINAGAR URBAN II.DIVSION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Urban | 90 | 1177 | 1115 | 86 | 0 | 13 | 1 | 8 | 95% |
CH. SAMBHAJINAGAR REGION | CH. SAMBHAJINAGAR ZONE | CH. SAMBHAJINAGAR (U) CIRCLE | CH. SAMBHAJINAGAR URBAN II.DIVSION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Urban | 7 | 20 | 13 | 23 | 0 | 6 | 0 | 2 | 65% |
CH. SAMBHAJINAGAR REGION | CH. SAMBHAJINAGAR ZONE | CH. SAMBHAJINAGAR (U) CIRCLE | CH. SAMBHAJINAGAR URBAN II.DIVSION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Urban | 90 | 15 | 10 | 48 | 0 | 10 | 6 | 6 | 67% |
CH. SAMBHAJINAGAR REGION | CH. SAMBHAJINAGAR ZONE | CH. SAMBHAJINAGAR CIRCLE | CH. SAMBHAJINAGAR RURAL I DIVN. | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 5453 | 5166 | 43 | 0 | 9 | 7 | 8 | 95% |
CH. SAMBHAJINAGAR REGION | CH. SAMBHAJINAGAR ZONE | CH. SAMBHAJINAGAR CIRCLE | CH. SAMBHAJINAGAR RURAL I DIVN. | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 419 | 341 | 89 | 0 | 7 | 0 | 1 | 81% |
CH. SAMBHAJINAGAR REGION | CH. SAMBHAJINAGAR ZONE | CH. SAMBHAJINAGAR CIRCLE | CH. SAMBHAJINAGAR RURAL I DIVN. | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 27 | 27 | 32 | 1 | 11 | 7 | 7 | 100% |
CH. SAMBHAJINAGAR REGION | CH. SAMBHAJINAGAR ZONE | CH. SAMBHAJINAGAR CIRCLE | CH. SAMBHAJINAGAR RURAL I DIVN. | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 7 | 5 | 88 | 3 | 30 | 3 | 21 | 71% |
CH. SAMBHAJINAGAR REGION | CH. SAMBHAJINAGAR ZONE | CH. SAMBHAJINAGAR CIRCLE | CH. SAMBHAJINAGAR RURAL II DIVN | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 2886 | 2699 | 95 | 0 | 11 | 5 | 8 | 94% |
CH. SAMBHAJINAGAR REGION | CH. SAMBHAJINAGAR ZONE | CH. SAMBHAJINAGAR CIRCLE | CH. SAMBHAJINAGAR RURAL II DIVN | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 156 | 83 | 141 | 0 | 35 | 18 | 31 | 53% |
CH. SAMBHAJINAGAR REGION | CH. SAMBHAJINAGAR ZONE | CH. SAMBHAJINAGAR CIRCLE | CH. SAMBHAJINAGAR RURAL II DIVN | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 30 | 30 | 30 | 0 | 4 | 0 | 2 | 100% |
CH. SAMBHAJINAGAR REGION | CH. SAMBHAJINAGAR ZONE | CH. SAMBHAJINAGAR CIRCLE | KANNAD DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 2101 | 2038 | 105 | 0 | 11 | 3 | 8 | 97% |
CH. SAMBHAJINAGAR REGION | CH. SAMBHAJINAGAR ZONE | CH. SAMBHAJINAGAR CIRCLE | KANNAD DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 521 | 313 | 99 | 0 | 24 | 11 | 11 | 60% |
CH. SAMBHAJINAGAR REGION | CH. SAMBHAJINAGAR ZONE | CH. SAMBHAJINAGAR CIRCLE | KANNAD DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 17 | 14 | 41 | 0 | 11 | 1 | 2 | 82% |
CH. SAMBHAJINAGAR REGION | CH. SAMBHAJINAGAR ZONE | CH. SAMBHAJINAGAR CIRCLE | KANNAD DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 6 | 4 | 1 | 0 | 0 | 0 | 0 | 67% |
CH. SAMBHAJINAGAR REGION | CH. SAMBHAJINAGAR ZONE | CH. SAMBHAJINAGAR CIRCLE | Sillod Division | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 1560 | 1518 | 58 | 0 | 7 | 2 | 6 | 97% |
CH. SAMBHAJINAGAR REGION | CH. SAMBHAJINAGAR ZONE | CH. SAMBHAJINAGAR CIRCLE | Sillod Division | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 73 | 54 | 85 | 2 | 47 | 35 | 57 | 74% |
CH. SAMBHAJINAGAR REGION | CH. SAMBHAJINAGAR ZONE | JALNA CIRCLE | JALNA DIVISION I | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 644 | 641 | 34 | 0 | 6 | 1 | 3 | 100% |
CH. SAMBHAJINAGAR REGION | CH. SAMBHAJINAGAR ZONE | JALNA CIRCLE | JALNA DIVISION I | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 4440 | 4270 | 101 | 0 | 6 | 1 | 3 | 96% |
CH. SAMBHAJINAGAR REGION | CH. SAMBHAJINAGAR ZONE | JALNA CIRCLE | JALNA DIVISION I | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 6 | 1 | 5 | 5 | 5 | 5 | 5 | 17% |
CH. SAMBHAJINAGAR REGION | CH. SAMBHAJINAGAR ZONE | JALNA CIRCLE | JALNA DIVISION II | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 1253 | 1240 | 111 | 0 | 7 | 1 | 3 | 99% |
CH. SAMBHAJINAGAR REGION | CH. SAMBHAJINAGAR ZONE | JALNA CIRCLE | JALNA DIVISION II | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 2100 | 1977 | 130 | 0 | 20 | 3 | 14 | 94% |
CH. SAMBHAJINAGAR REGION | CH. SAMBHAJINAGAR ZONE | JALNA CIRCLE | JALNA DIVISION II | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 3 | 3 | 9 | 0 | 5 | 0 | 6 | 100% |
CH. SAMBHAJINAGAR REGION | CH. SAMBHAJINAGAR ZONE | JALNA CIRCLE | JALNA DIVISION II | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 5 | 3 | 25 | 1 | 12 | 1 | 9 | 60% |
CH. SAMBHAJINAGAR REGION | LATUR ZONE, LATUR | BEED CIRCLE | AMBEJOGAI DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 537 | 486 | 133 | 0 | 9 | 1 | 4 | 91% |
CH. SAMBHAJINAGAR REGION | LATUR ZONE, LATUR | BEED CIRCLE | AMBEJOGAI DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 1653 | 1372 | 126 | 0 | 23 | 2 | 16 | 83% |
CH. SAMBHAJINAGAR REGION | LATUR ZONE, LATUR | BEED CIRCLE | AMBEJOGAI DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 4 | 3 | 1 | 0 | 0 | 0 | 0 | 75% |
CH. SAMBHAJINAGAR REGION | LATUR ZONE, LATUR | BEED CIRCLE | AMBEJOGAI DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 5 | 4 | 19 | 1 | 8 | 1 | 7 | 80% |
CH. SAMBHAJINAGAR REGION | LATUR ZONE, LATUR | BEED CIRCLE | BEED DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 1102 | 996 | 116 | 0 | 12 | 1 | 6 | 90% |
CH. SAMBHAJINAGAR REGION | LATUR ZONE, LATUR | BEED CIRCLE | BEED DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 868 | 680 | 154 | 0 | 21 | 1 | 10 | 78% |
CH. SAMBHAJINAGAR REGION | LATUR ZONE, LATUR | BEED CIRCLE | BEED DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 10 | 10 | 20 | 0 | 4 | 0 | 2 | 100% |
CH. SAMBHAJINAGAR REGION | LATUR ZONE, LATUR | BEED CIRCLE | BEED DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 2 | 1 | 87 | 87 | 87 | 87 | 87 | 50% |
CH. SAMBHAJINAGAR REGION | LATUR ZONE, LATUR | DHARASHIV CIRCLE | DHARASHIV DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 1201 | 1157 | 144 | 0 | 14 | 1 | 9 | 96% |
CH. SAMBHAJINAGAR REGION | LATUR ZONE, LATUR | DHARASHIV CIRCLE | DHARASHIV DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 1019 | 784 | 156 | 0 | 23 | 1 | 16 | 77% |
CH. SAMBHAJINAGAR REGION | LATUR ZONE, LATUR | DHARASHIV CIRCLE | DHARASHIV DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 9 | 9 | 44 | 0 | 9 | 0 | 1 | 100% |
CH. SAMBHAJINAGAR REGION | LATUR ZONE, LATUR | DHARASHIV CIRCLE | DHARASHIV DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 9 | 8 | 24 | 1 | 9 | 13 | 8 | 89% |
CH. SAMBHAJINAGAR REGION | LATUR ZONE, LATUR | DHARASHIV CIRCLE | TULJAPUR DIVSION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 416 | 380 | 120 | 0 | 14 | 2 | 9 | 91% |
CH. SAMBHAJINAGAR REGION | LATUR ZONE, LATUR | DHARASHIV CIRCLE | TULJAPUR DIVSION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 1452 | 1230 | 156 | 0 | 15 | 3 | 9 | 85% |
CH. SAMBHAJINAGAR REGION | LATUR ZONE, LATUR | DHARASHIV CIRCLE | TULJAPUR DIVSION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 5 | 4 | 19 | 1 | 9 | 1 | 7 | 80% |
CH. SAMBHAJINAGAR REGION | LATUR ZONE, LATUR | DHARASHIV CIRCLE | TULJAPUR DIVSION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 5 | 2 | 1 | 1 | 1 | 1 | 1 | 40% |
CH. SAMBHAJINAGAR REGION | LATUR ZONE, LATUR | LATUR CIRCLE | LATUR DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 246 | 244 | 124 | 0 | 12 | 0 | 8 | 99% |
CH. SAMBHAJINAGAR REGION | LATUR ZONE, LATUR | LATUR CIRCLE | LATUR DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Urban | 7 | 190 | 190 | 33 | 0 | 6 | 7 | 6 | 100% |
CH. SAMBHAJINAGAR REGION | LATUR ZONE, LATUR | LATUR CIRCLE | LATUR DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 1501 | 1340 | 167 | 0 | 17 | 1 | 13 | 89% |
CH. SAMBHAJINAGAR REGION | LATUR ZONE, LATUR | LATUR CIRCLE | LATUR DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Urban | 90 | 1511 | 1472 | 106 | 0 | 8 | 1 | 5 | 97% |
CH. SAMBHAJINAGAR REGION | LATUR ZONE, LATUR | LATUR CIRCLE | LATUR DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 1 | 1 | 10 | 10 | 10 | 10 | 10 | 100% |
CH. SAMBHAJINAGAR REGION | LATUR ZONE, LATUR | LATUR CIRCLE | LATUR DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Urban | 7 | 16 | 15 | 4 | 0 | 1 | 0 | 1 | 94% |
CH. SAMBHAJINAGAR REGION | LATUR ZONE, LATUR | LATUR CIRCLE | LATUR DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 7 | 7 | 19 | 1 | 5 | 1 | 2 | 100% |
CH. SAMBHAJINAGAR REGION | LATUR ZONE, LATUR | LATUR CIRCLE | LATUR DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Urban | 90 | 39 | 39 | 15 | 0 | 3 | 1 | 1 | 100% |
CH. SAMBHAJINAGAR REGION | LATUR ZONE, LATUR | LATUR CIRCLE | NILANGA DIVSION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 625 | 583 | 59 | 0 | 14 | 2 | 14 | 93% |
CH. SAMBHAJINAGAR REGION | LATUR ZONE, LATUR | LATUR CIRCLE | NILANGA DIVSION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 1691 | 1178 | 122 | 0 | 25 | 26 | 21 | 70% |
CH. SAMBHAJINAGAR REGION | LATUR ZONE, LATUR | LATUR CIRCLE | NILANGA DIVSION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 2 | 1 | 1 | 1 | 1 | 1 | 1 | 50% |
CH. SAMBHAJINAGAR REGION | LATUR ZONE, LATUR | LATUR CIRCLE | NILANGA DIVSION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 9 | 6 | 27 | 0 | 10 | 0 | 4 | 67% |
CH. SAMBHAJINAGAR REGION | LATUR ZONE, LATUR | LATUR CIRCLE | UDGIR DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 1079 | 1044 | 96 | 0 | 18 | 3 | 13 | 97% |
CH. SAMBHAJINAGAR REGION | LATUR ZONE, LATUR | LATUR CIRCLE | UDGIR DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 1528 | 1252 | 149 | 0 | 25 | 1 | 17 | 82% |
CH. SAMBHAJINAGAR REGION | LATUR ZONE, LATUR | LATUR CIRCLE | UDGIR DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 10 | 9 | 41 | 0 | 13 | 0 | 9 | 90% |
CH. SAMBHAJINAGAR REGION | LATUR ZONE, LATUR | LATUR CIRCLE | UDGIR DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 3 | 1 | 16 | 16 | 16 | 16 | 16 | 33% |
CH. SAMBHAJINAGAR REGION | NANDED ZONE | HINGOLI CIRCLE | HINGOLI DIVSION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 3058 | 2986 | 122 | 0 | 12 | 2 | 8 | 98% |
CH. SAMBHAJINAGAR REGION | NANDED ZONE | HINGOLI CIRCLE | HINGOLI DIVSION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 34 | 24 | 109 | 0 | 31 | 0 | 24 | 71% |
CH. SAMBHAJINAGAR REGION | NANDED ZONE | HINGOLI CIRCLE | HINGOLI DIVSION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 7 | 5 | 27 | 0 | 8 | 0 | 4 | 71% |
CH. SAMBHAJINAGAR REGION | NANDED ZONE | HINGOLI CIRCLE | HINGOLI DIVSION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 1 | 0 | 0 | 0 | 0 | 0 | 0 | 0% |
CH. SAMBHAJINAGAR REGION | NANDED ZONE | NANDED CIRCLE | BHOKAR DIVSION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 2130 | 2109 | 118 | 0 | 11 | 2 | 6 | 99% |
CH. SAMBHAJINAGAR REGION | NANDED ZONE | NANDED CIRCLE | BHOKAR DIVSION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 80 | 60 | 92 | 3 | 31 | 24 | 25 | 75% |
CH. SAMBHAJINAGAR REGION | NANDED ZONE | NANDED CIRCLE | BHOKAR DIVSION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 5 | 5 | 53 | 4 | 23 | 4 | 23 | 100% |
CH. SAMBHAJINAGAR REGION | NANDED ZONE | NANDED CIRCLE | DEGLOOR DIVSION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 2408 | 2324 | 155 | 0 | 21 | 4 | 14 | 97% |
CH. SAMBHAJINAGAR REGION | NANDED ZONE | NANDED CIRCLE | DEGLOOR DIVSION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 18 | 5 | 121 | 11 | 61 | 11 | 44 | 28% |
CH. SAMBHAJINAGAR REGION | NANDED ZONE | NANDED CIRCLE | DEGLOOR DIVSION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 5 | 5 | 8 | 1 | 4 | 1 | 3 | 100% |
CH. SAMBHAJINAGAR REGION | NANDED ZONE | NANDED CIRCLE | DEGLOOR DIVSION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 1 | 1 | 3 | 3 | 3 | 3 | 3 | 100% |
CH. SAMBHAJINAGAR REGION | NANDED ZONE | NANDED CIRCLE | NANDED DIVSION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 125 | 123 | 103 | 1 | 17 | 4 | 9 | 98% |
CH. SAMBHAJINAGAR REGION | NANDED ZONE | NANDED CIRCLE | NANDED DIVSION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Urban | 7 | 2547 | 2519 | 156 | 0 | 12 | 4 | 8 | 99% |
CH. SAMBHAJINAGAR REGION | NANDED ZONE | NANDED CIRCLE | NANDED DIVSION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 2 | 1 | 6 | 6 | 6 | 6 | 6 | 50% |
CH. SAMBHAJINAGAR REGION | NANDED ZONE | NANDED CIRCLE | NANDED DIVSION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Urban | 90 | 52 | 24 | 73 | 0 | 15 | 0 | 11 | 46% |
CH. SAMBHAJINAGAR REGION | NANDED ZONE | NANDED CIRCLE | NANDED DIVSION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 3 | 0 | 0 | 0 | 0 | 0 | 0 | 0% |
CH. SAMBHAJINAGAR REGION | NANDED ZONE | NANDED CIRCLE | NANDED DIVSION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Urban | 7 | 10 | 8 | 25 | 0 | 7 | 0 | 5 | 80% |
CH. SAMBHAJINAGAR REGION | NANDED ZONE | NANDED CIRCLE | NANDED RURAL DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 1496 | 1462 | 134 | 0 | 10 | 2 | 6 | 98% |
CH. SAMBHAJINAGAR REGION | NANDED ZONE | NANDED CIRCLE | NANDED RURAL DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 54 | 36 | 155 | 0 | 31 | 9 | 17 | 67% |
CH. SAMBHAJINAGAR REGION | NANDED ZONE | NANDED CIRCLE | NANDED RURAL DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 2 | 2 | 4 | 0 | 2 | 0 | 2 | 100% |
CH. SAMBHAJINAGAR REGION | NANDED ZONE | PARBHANI CIRCLE | PARBHANI DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 1772 | 1746 | 162 | 0 | 23 | 1 | 14 | 99% |
CH. SAMBHAJINAGAR REGION | NANDED ZONE | PARBHANI CIRCLE | PARBHANI DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Urban | 7 | 798 | 794 | 159 | 0 | 21 | 8 | 14 | 99% |
CH. SAMBHAJINAGAR REGION | NANDED ZONE | PARBHANI CIRCLE | PARBHANI DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 39 | 9 | 92 | 10 | 49 | 44 | 44 | 23% |
CH. SAMBHAJINAGAR REGION | NANDED ZONE | PARBHANI CIRCLE | PARBHANI DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Urban | 90 | 7 | 2 | 47 | 18 | 33 | 18 | 33 | 29% |
CH. SAMBHAJINAGAR REGION | NANDED ZONE | PARBHANI CIRCLE | PARBHANI DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 4 | 2 | 15 | 0 | 8 | 0 | 8 | 50% |
CH. SAMBHAJINAGAR REGION | NANDED ZONE | PARBHANI CIRCLE | PARBHANI DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Urban | 7 | 9 | 8 | 54 | 0 | 16 | 1 | 3 | 89% |
CH. SAMBHAJINAGAR REGION | NANDED ZONE | PARBHANI CIRCLE | PARBHANI DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 1 | 0 | 0 | 0 | 0 | 0 | 0 | 0% |
CH. SAMBHAJINAGAR REGION | NANDED ZONE | PARBHANI CIRCLE | SELU DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 2175 | 2044 | 154 | 0 | 16 | 0 | 9 | 94% |
CH. SAMBHAJINAGAR REGION | NANDED ZONE | PARBHANI CIRCLE | SELU DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 34 | 18 | 91 | 0 | 33 | 51 | 34 | 53% |
CH. SAMBHAJINAGAR REGION | NANDED ZONE | PARBHANI CIRCLE | SELU DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 2 | 0 | 0 | 0 | 0 | 0 | 0 | 0% |
CH. SAMBHAJINAGAR REGION | NANDED ZONE | PARBHANI CIRCLE | SELU DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 100% |
KOKAN REGION | BHANDUP (U) ZONE | PEN CIRCLE | ALIBAUG DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 2992 | 2897 | 116 | 0 | 5 | 1 | 3 | 97% |
KOKAN REGION | BHANDUP (U) ZONE | PEN CIRCLE | ALIBAUG DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 169 | 138 | 90 | 1 | 19 | 1 | 10 | 82% |
KOKAN REGION | BHANDUP (U) ZONE | PEN CIRCLE | ALIBAUG DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 91 | 89 | 71 | 0 | 14 | 1 | 7 | 98% |
KOKAN REGION | BHANDUP (U) ZONE | PEN CIRCLE | ALIBAUG DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 10 | 7 | 55 | 0 | 27 | 55 | 20 | 70% |
KOKAN REGION | BHANDUP (U) ZONE | PEN CIRCLE | GOREGAON DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 1929 | 1877 | 83 | 0 | 7 | 2 | 5 | 97% |
KOKAN REGION | BHANDUP (U) ZONE | PEN CIRCLE | GOREGAON DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 87 | 48 | 137 | 1 | 55 | 95 | 51 | 55% |
KOKAN REGION | BHANDUP (U) ZONE | PEN CIRCLE | GOREGAON DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 95 | 92 | 47 | 0 | 6 | 0 | 1 | 97% |
KOKAN REGION | BHANDUP (U) ZONE | PEN CIRCLE | GOREGAON DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 2 | 1 | 12 | 12 | 12 | 12 | 12 | 50% |
KOKAN REGION | BHANDUP (U) ZONE | PEN CIRCLE | PANVEL RURAL DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 7494 | 7107 | 79 | 0 | 9 | 4 | 7 | 95% |
KOKAN REGION | BHANDUP (U) ZONE | PEN CIRCLE | PANVEL RURAL DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 684 | 610 | 86 | 0 | 28 | 26 | 21 | 89% |
KOKAN REGION | BHANDUP (U) ZONE | PEN CIRCLE | PANVEL RURAL DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 61 | 52 | 78 | 0 | 16 | 0 | 13 | 85% |
KOKAN REGION | BHANDUP (U) ZONE | PEN CIRCLE | PANVEL RURAL DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 6 | 3 | 31 | 13 | 20 | 13 | 17 | 50% |
KOKAN REGION | BHANDUP (U) ZONE | PEN CIRCLE | ROHA DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 2821 | 2725 | 89 | 0 | 4 | 1 | 3 | 97% |
KOKAN REGION | BHANDUP (U) ZONE | PEN CIRCLE | ROHA DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 134 | 93 | 66 | 1 | 20 | 35 | 14 | 69% |
KOKAN REGION | BHANDUP (U) ZONE | PEN CIRCLE | ROHA DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 52 | 45 | 28 | 0 | 6 | 3 | 4 | 87% |
KOKAN REGION | BHANDUP (U) ZONE | PEN CIRCLE | ROHA DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 6 | 5 | 58 | 6 | 35 | 6 | 28 | 83% |
KOKAN REGION | BHANDUP (U) ZONE | THANE (U) CIRCLE | BHANDUP URBAN DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Metro | 3 | 832 | 825 | 20 | 0 | 4 | 1 | 3 | 99% |
KOKAN REGION | BHANDUP (U) ZONE | THANE (U) CIRCLE | BHANDUP URBAN DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Metro | 90 | 3011 | 2832 | 78 | 0 | 10 | 4 | 5 | 94% |
KOKAN REGION | BHANDUP (U) ZONE | THANE (U) CIRCLE | BHANDUP URBAN DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Metro | 3 | 49 | 42 | 8 | 0 | 2 | 1 | 1 | 86% |
KOKAN REGION | BHANDUP (U) ZONE | THANE (U) CIRCLE | BHANDUP URBAN DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Metro | 90 | 78 | 60 | 83 | 0 | 4 | 0 | 1 | 77% |
KOKAN REGION | BHANDUP (U) ZONE | THANE (U) CIRCLE | MULUND DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Metro | 3 | 483 | 479 | 15 | 0 | 3 | 1 | 2 | 99% |
KOKAN REGION | BHANDUP (U) ZONE | THANE (U) CIRCLE | MULUND DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Metro | 90 | 2808 | 2533 | 119 | 0 | 7 | 3 | 4 | 90% |
KOKAN REGION | BHANDUP (U) ZONE | THANE (U) CIRCLE | MULUND DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Metro | 3 | 35 | 35 | 7 | 0 | 1 | 0 | 0 | 100% |
KOKAN REGION | BHANDUP (U) ZONE | THANE (U) CIRCLE | MULUND DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Metro | 90 | 130 | 114 | 38 | 0 | 2 | 1 | 1 | 88% |
KOKAN REGION | BHANDUP (U) ZONE | THANE (U) CIRCLE | THANE DIVISION-I | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Metro | 3 | 384 | 382 | 19 | 0 | 2 | 0 | 1 | 99% |
KOKAN REGION | BHANDUP (U) ZONE | THANE (U) CIRCLE | THANE DIVISION-I | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Metro | 90 | 343 | 330 | 21 | 0 | 3 | 1 | 2 | 96% |
KOKAN REGION | BHANDUP (U) ZONE | THANE (U) CIRCLE | THANE DIVISION-I | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Metro | 3 | 45 | 41 | 20 | 0 | 2 | 0 | 1 | 91% |
KOKAN REGION | BHANDUP (U) ZONE | THANE (U) CIRCLE | THANE DIVISION-I | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Metro | 90 | 48 | 41 | 35 | 0 | 2 | 0 | 1 | 85% |
KOKAN REGION | BHANDUP (U) ZONE | THANE (U) CIRCLE | THANE DIVISION-II | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Metro | 3 | 248 | 243 | 14 | 0 | 2 | 1 | 1 | 98% |
KOKAN REGION | BHANDUP (U) ZONE | THANE (U) CIRCLE | THANE DIVISION-II | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Metro | 90 | 2603 | 2256 | 115 | 0 | 15 | 0 | 8 | 87% |
KOKAN REGION | BHANDUP (U) ZONE | THANE (U) CIRCLE | THANE DIVISION-II | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Metro | 3 | 28 | 27 | 9 | 0 | 1 | 0 | 0 | 96% |
KOKAN REGION | BHANDUP (U) ZONE | THANE (U) CIRCLE | THANE DIVISION-II | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Metro | 90 | 63 | 53 | 69 | 0 | 7 | 0 | 3 | 84% |
KOKAN REGION | BHANDUP (U) ZONE | THANE (U) CIRCLE | WAGLE ESTATE DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Metro | 3 | 534 | 526 | 8 | 0 | 2 | 2 | 2 | 99% |
KOKAN REGION | BHANDUP (U) ZONE | THANE (U) CIRCLE | WAGLE ESTATE DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Metro | 90 | 4907 | 4409 | 94 | 0 | 8 | 1 | 3 | 90% |
KOKAN REGION | BHANDUP (U) ZONE | THANE (U) CIRCLE | WAGLE ESTATE DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Metro | 3 | 58 | 57 | 8 | 0 | 1 | 1 | 1 | 98% |
KOKAN REGION | BHANDUP (U) ZONE | THANE (U) CIRCLE | WAGLE ESTATE DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Metro | 90 | 70 | 51 | 107 | 0 | 6 | 0 | 1 | 73% |
KOKAN REGION | BHANDUP (U) ZONE | WASHI CIRCLE | NERUL O DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Metro | 3 | 5089 | 5011 | 84 | 0 | 4 | 1 | 3 | 98% |
KOKAN REGION | BHANDUP (U) ZONE | WASHI CIRCLE | NERUL O DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Metro | 90 | 2490 | 2217 | 103 | 0 | 14 | 1 | 9 | 89% |
KOKAN REGION | BHANDUP (U) ZONE | WASHI CIRCLE | NERUL O DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Metro | 3 | 191 | 169 | 56 | 0 | 5 | 0 | 1 | 88% |
KOKAN REGION | BHANDUP (U) ZONE | WASHI CIRCLE | NERUL O DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Metro | 90 | 41 | 32 | 81 | 0 | 13 | 1 | 4 | 78% |
KOKAN REGION | BHANDUP (U) ZONE | WASHI CIRCLE | PANVEL URBAN DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Metro | 3 | 1531 | 1498 | 37 | 0 | 4 | 1 | 3 | 98% |
KOKAN REGION | BHANDUP (U) ZONE | WASHI CIRCLE | PANVEL URBAN DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 3014 | 2980 | 42 | 0 | 5 | 3 | 4 | 99% |
KOKAN REGION | BHANDUP (U) ZONE | WASHI CIRCLE | PANVEL URBAN DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Metro | 90 | 3450 | 3061 | 122 | 0 | 8 | 1 | 5 | 89% |
KOKAN REGION | BHANDUP (U) ZONE | WASHI CIRCLE | PANVEL URBAN DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 5172 | 4550 | 117 | 0 | 11 | 2 | 8 | 88% |
KOKAN REGION | BHANDUP (U) ZONE | WASHI CIRCLE | PANVEL URBAN DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Metro | 3 | 74 | 66 | 81 | 0 | 5 | 0 | 1 | 89% |
KOKAN REGION | BHANDUP (U) ZONE | WASHI CIRCLE | PANVEL URBAN DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 63 | 53 | 25 | 0 | 4 | 2 | 3 | 84% |
KOKAN REGION | BHANDUP (U) ZONE | WASHI CIRCLE | PANVEL URBAN DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Metro | 90 | 108 | 96 | 68 | 0 | 9 | 0 | 4 | 89% |
KOKAN REGION | BHANDUP (U) ZONE | WASHI CIRCLE | PANVEL URBAN DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 47 | 45 | 45 | 0 | 9 | 2 | 5 | 96% |
KOKAN REGION | BHANDUP (U) ZONE | WASHI CIRCLE | WASHI DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Metro | 3 | 864 | 860 | 43 | 0 | 6 | 2 | 4 | 100% |
KOKAN REGION | BHANDUP (U) ZONE | WASHI CIRCLE | WASHI DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Metro | 90 | 4887 | 4714 | 120 | 0 | 8 | 1 | 5 | 96% |
KOKAN REGION | BHANDUP (U) ZONE | WASHI CIRCLE | WASHI DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Metro | 3 | 26 | 23 | 53 | 0 | 11 | 2 | 4 | 88% |
KOKAN REGION | BHANDUP (U) ZONE | WASHI CIRCLE | WASHI DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Metro | 90 | 196 | 144 | 69 | 0 | 6 | 1 | 3 | 73% |
KOKAN REGION | JALGAON ZONE | DHULE CIRCLE | DHULE RURAL DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 1559 | 1439 | 130 | 0 | 14 | 7 | 10 | 92% |
KOKAN REGION | JALGAON ZONE | DHULE CIRCLE | DHULE RURAL DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 43 | 29 | 121 | 0 | 30 | 0 | 22 | 67% |
KOKAN REGION | JALGAON ZONE | DHULE CIRCLE | DHULE RURAL DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 1 | 1 | 3 | 3 | 3 | 3 | 3 | 100% |
KOKAN REGION | JALGAON ZONE | DHULE CIRCLE | DHULE URBAN DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 1132 | 1104 | 100 | 0 | 17 | 3 | 13 | 98% |
KOKAN REGION | JALGAON ZONE | DHULE CIRCLE | DHULE URBAN DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Urban | 7 | 1197 | 1181 | 123 | 0 | 15 | 2 | 9 | 99% |
KOKAN REGION | JALGAON ZONE | DHULE CIRCLE | DHULE URBAN DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 31 | 19 | 136 | 0 | 41 | 0 | 36 | 61% |
KOKAN REGION | JALGAON ZONE | DHULE CIRCLE | DHULE URBAN DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Urban | 90 | 24 | 21 | 44 | 1 | 7 | 7 | 7 | 88% |
KOKAN REGION | JALGAON ZONE | DHULE CIRCLE | DHULE URBAN DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 1 | 1 | 30 | 30 | 30 | 30 | 30 | 100% |
KOKAN REGION | JALGAON ZONE | DHULE CIRCLE | DHULE URBAN DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Urban | 7 | 12 | 10 | 3 | 0 | 1 | 0 | 2 | 83% |
KOKAN REGION | JALGAON ZONE | DHULE CIRCLE | DONDAICHA DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 1704 | 1685 | 114 | 0 | 14 | 1 | 8 | 99% |
KOKAN REGION | JALGAON ZONE | DHULE CIRCLE | DONDAICHA DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 250 | 218 | 79 | 0 | 20 | 12 | 12 | 87% |
KOKAN REGION | JALGAON ZONE | DHULE CIRCLE | DONDAICHA DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 12 | 12 | 18 | 0 | 3 | 0 | 0 | 100% |
KOKAN REGION | JALGAON ZONE | DHULE CIRCLE | DONDAICHA DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 1 | 1 | 35 | 35 | 35 | 35 | 35 | 100% |
KOKAN REGION | JALGAON ZONE | JALGAON CIRCLE | BHUSAWAL UCR DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 1919 | 1780 | 130 | 0 | 21 | 7 | 16 | 93% |
KOKAN REGION | JALGAON ZONE | JALGAON CIRCLE | BHUSAWAL UCR DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 163 | 106 | 138 | 1 | 39 | 32 | 32 | 65% |
KOKAN REGION | JALGAON ZONE | JALGAON CIRCLE | BHUSAWAL UCR DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 5 | 5 | 12 | 0 | 5 | 0 | 1 | 100% |
KOKAN REGION | JALGAON ZONE | JALGAON CIRCLE | BHUSAWAL UCR DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 1 | 0 | 0 | 0 | 0 | 0 | 0 | 0% |
KOKAN REGION | JALGAON ZONE | JALGAON CIRCLE | CHALISGAON DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 1927 | 1893 | 158 | 0 | 9 | 1 | 5 | 98% |
KOKAN REGION | JALGAON ZONE | JALGAON CIRCLE | CHALISGAON DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 110 | 92 | 132 | 0 | 28 | 4 | 27 | 84% |
KOKAN REGION | JALGAON ZONE | JALGAON CIRCLE | CHALISGAON DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 5 | 5 | 14 | 0 | 5 | 0 | 1 | 100% |
KOKAN REGION | JALGAON ZONE | JALGAON CIRCLE | DHARANGAON DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 2811 | 2739 | 139 | 0 | 18 | 6 | 14 | 97% |
KOKAN REGION | JALGAON ZONE | JALGAON CIRCLE | DHARANGAON DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 105 | 50 | 144 | 0 | 24 | 3 | 6 | 48% |
KOKAN REGION | JALGAON ZONE | JALGAON CIRCLE | DHARANGAON DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 22 | 20 | 42 | 4 | 13 | 6 | 7 | 91% |
KOKAN REGION | JALGAON ZONE | JALGAON CIRCLE | DHARANGAON DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 1 | 0 | 0 | 0 | 0 | 0 | 0 | 0% |
KOKAN REGION | JALGAON ZONE | JALGAON CIRCLE | JALGAON URBAN DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 894 | 867 | 155 | 0 | 17 | 4 | 13 | 97% |
KOKAN REGION | JALGAON ZONE | JALGAON CIRCLE | JALGAON URBAN DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Urban | 7 | 1937 | 1884 | 149 | 0 | 11 | 0 | 5 | 97% |
KOKAN REGION | JALGAON ZONE | JALGAON CIRCLE | JALGAON URBAN DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 23 | 8 | 71 | 6 | 37 | 31 | 31 | 35% |
KOKAN REGION | JALGAON ZONE | JALGAON CIRCLE | JALGAON URBAN DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Urban | 90 | 264 | 134 | 125 | 0 | 44 | 64 | 45 | 51% |
KOKAN REGION | JALGAON ZONE | JALGAON CIRCLE | JALGAON URBAN DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 1 | 1 | 4 | 4 | 4 | 4 | 4 | 100% |
KOKAN REGION | JALGAON ZONE | JALGAON CIRCLE | JALGAON URBAN DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Urban | 7 | 90 | 83 | 74 | 0 | 7 | 0 | 3 | 92% |
KOKAN REGION | JALGAON ZONE | JALGAON CIRCLE | MUKTAINAGAR DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 1034 | 937 | 162 | 0 | 23 | 12 | 18 | 91% |
KOKAN REGION | JALGAON ZONE | JALGAON CIRCLE | MUKTAINAGAR DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 71 | 24 | 141 | 0 | 38 | 2 | 15 | 34% |
KOKAN REGION | JALGAON ZONE | JALGAON CIRCLE | MUKTAINAGAR DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 2 | 2 | 9 | 3 | 6 | 3 | 6 | 100% |
KOKAN REGION | JALGAON ZONE | JALGAON CIRCLE | MUKTAINAGAR DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 1 | 0 | 0 | 0 | 0 | 0 | 0 | 0% |
KOKAN REGION | JALGAON ZONE | JALGAON CIRCLE | PACHORA DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 1380 | 1351 | 152 | 0 | 15 | 2 | 11 | 98% |
KOKAN REGION | JALGAON ZONE | JALGAON CIRCLE | PACHORA DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 37 | 14 | 79 | 1 | 31 | 1 | 21 | 38% |
KOKAN REGION | JALGAON ZONE | JALGAON CIRCLE | PACHORA DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 6 | 6 | 67 | 1 | 21 | 1 | 9 | 100% |
KOKAN REGION | JALGAON ZONE | JALGAON CIRCLE | PACHORA DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 1 | 1 | 23 | 23 | 23 | 23 | 23 | 100% |
KOKAN REGION | JALGAON ZONE | JALGAON CIRCLE | SAVADA DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 1897 | 1872 | 139 | 0 | 15 | 4 | 10 | 99% |
KOKAN REGION | JALGAON ZONE | JALGAON CIRCLE | SAVADA DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 62 | 55 | 107 | 1 | 33 | 19 | 23 | 89% |
KOKAN REGION | JALGAON ZONE | JALGAON CIRCLE | SAVADA DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 1 | 1 | 28 | 28 | 28 | 28 | 28 | 100% |
KOKAN REGION | JALGAON ZONE | NANDURBAR CIRCLE | NANDURBAR (O) DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 1439 | 1339 | 118 | 0 | 16 | 6 | 11 | 93% |
KOKAN REGION | JALGAON ZONE | NANDURBAR CIRCLE | NANDURBAR (O) DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 56 | 21 | 102 | 5 | 42 | 56 | 35 | 38% |
KOKAN REGION | JALGAON ZONE | NANDURBAR CIRCLE | NANDURBAR (O) DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 15 | 13 | 39 | 0 | 12 | 0 | 6 | 87% |
KOKAN REGION | JALGAON ZONE | NANDURBAR CIRCLE | NANDURBAR (O) DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 1 | 1 | 49 | 49 | 49 | 49 | 49 | 100% |
KOKAN REGION | JALGAON ZONE | NANDURBAR CIRCLE | SHAHADA DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 1364 | 1315 | 101 | 0 | 7 | 1 | 4 | 96% |
KOKAN REGION | JALGAON ZONE | NANDURBAR CIRCLE | SHAHADA DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 1142 | 200 | 93 | 0 | 65 | 77 | 78 | 18% |
KOKAN REGION | JALGAON ZONE | NANDURBAR CIRCLE | SHAHADA DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 7 | 7 | 22 | 0 | 10 | 1 | 11 | 100% |
KOKAN REGION | KALYAN ZONE | KALYAN CIRCLE - I | DOMBIVALI URBAN DIVSION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Metro | 3 | 1730 | 1663 | 34 | 0 | 4 | 2 | 3 | 96% |
KOKAN REGION | KALYAN ZONE | KALYAN CIRCLE - I | DOMBIVALI URBAN DIVSION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Metro | 90 | 221 | 218 | 26 | 0 | 4 | 1 | 3 | 99% |
KOKAN REGION | KALYAN ZONE | KALYAN CIRCLE - I | DOMBIVALI URBAN DIVSION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Metro | 3 | 103 | 97 | 42 | 0 | 3 | 1 | 1 | 94% |
KOKAN REGION | KALYAN ZONE | KALYAN CIRCLE - I | DOMBIVALI URBAN DIVSION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Metro | 90 | 4 | 4 | 2 | 0 | 1 | 2 | 2 | 100% |
KOKAN REGION | KALYAN ZONE | KALYAN CIRCLE - I | KALYAN (EAST) DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Metro | 3 | 10870 | 10680 | 85 | 0 | 5 | 1 | 3 | 98% |
KOKAN REGION | KALYAN ZONE | KALYAN CIRCLE - I | KALYAN (EAST) DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Metro | 90 | 521 | 439 | 170 | 0 | 15 | 1 | 4 | 84% |
KOKAN REGION | KALYAN ZONE | KALYAN CIRCLE - I | KALYAN (EAST) DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Metro | 3 | 84 | 59 | 111 | 0 | 12 | 1 | 2 | 70% |
KOKAN REGION | KALYAN ZONE | KALYAN CIRCLE - I | KALYAN (EAST) DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Metro | 90 | 3 | 3 | 121 | 0 | 43 | 0 | 8 | 100% |
KOKAN REGION | KALYAN ZONE | KALYAN CIRCLE - I | KALYAN URBAN DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Metro | 3 | 3005 | 2921 | 54 | 0 | 5 | 2 | 3 | 97% |
KOKAN REGION | KALYAN ZONE | KALYAN CIRCLE - I | KALYAN URBAN DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Metro | 90 | 319 | 126 | 119 | 1 | 15 | 10 | 10 | 39% |
KOKAN REGION | KALYAN ZONE | KALYAN CIRCLE - I | KALYAN URBAN DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Metro | 3 | 52 | 49 | 14 | 0 | 2 | 1 | 1 | 94% |
KOKAN REGION | KALYAN ZONE | KALYAN CIRCLE - I | KALYAN URBAN DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Metro | 90 | 1 | 1 | 9 | 9 | 9 | 9 | 9 | 100% |
KOKAN REGION | KALYAN ZONE | KALYAN CIRCLE - II | BADLAPUR DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 6827 | 6726 | 109 | 0 | 6 | 2 | 5 | 99% |
KOKAN REGION | KALYAN ZONE | KALYAN CIRCLE - II | BADLAPUR DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 134 | 107 | 77 | 2 | 27 | 7 | 18 | 80% |
KOKAN REGION | KALYAN ZONE | KALYAN CIRCLE - II | BADLAPUR DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 69 | 63 | 40 | 0 | 10 | 0 | 6 | 91% |
KOKAN REGION | KALYAN ZONE | KALYAN CIRCLE - II | KALYAN RURAL DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 6160 | 6047 | 98 | 0 | 4 | 0 | 2 | 98% |
KOKAN REGION | KALYAN ZONE | KALYAN CIRCLE - II | KALYAN RURAL DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 130 | 112 | 139 | 0 | 17 | 1 | 9 | 86% |
KOKAN REGION | KALYAN ZONE | KALYAN CIRCLE - II | KALYAN RURAL DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 21 | 20 | 34 | 0 | 8 | 3 | 4 | 95% |
KOKAN REGION | KALYAN ZONE | KALYAN CIRCLE - II | KALYAN RURAL DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 100% |
KOKAN REGION | KALYAN ZONE | KALYAN CIRCLE - II | ULHASNAGAR DIVISION I | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Urban | 7 | 1723 | 1687 | 96 | 0 | 8 | 2 | 5 | 98% |
KOKAN REGION | KALYAN ZONE | KALYAN CIRCLE - II | ULHASNAGAR DIVISION I | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Urban | 7 | 18 | 15 | 42 | 0 | 8 | 0 | 1 | 83% |
KOKAN REGION | KALYAN ZONE | KALYAN CIRCLE - II | ULHASNAGAR DIVISION II | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Urban | 7 | 3262 | 3173 | 73 | 0 | 4 | 0 | 1 | 97% |
KOKAN REGION | KALYAN ZONE | KALYAN CIRCLE - II | ULHASNAGAR DIVISION II | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Urban | 90 | 144 | 111 | 90 | 0 | 20 | 1 | 14 | 77% |
KOKAN REGION | KALYAN ZONE | KALYAN CIRCLE - II | ULHASNAGAR DIVISION II | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Urban | 7 | 60 | 58 | 27 | 0 | 4 | 0 | 1 | 97% |
KOKAN REGION | KALYAN ZONE | KALYAN CIRCLE - II | ULHASNAGAR DIVISION II | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Urban | 90 | 18 | 10 | 69 | 0 | 17 | 1 | 5 | 56% |
KOKAN REGION | KALYAN ZONE | PALGHAR (MINI) CIRCLE | PALGHAR DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 14328 | 13748 | 106 | 0 | 11 | 2 | 7 | 96% |
KOKAN REGION | KALYAN ZONE | PALGHAR (MINI) CIRCLE | PALGHAR DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 812 | 588 | 128 | 0 | 15 | 1 | 6 | 72% |
KOKAN REGION | KALYAN ZONE | PALGHAR (MINI) CIRCLE | PALGHAR DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 232 | 208 | 125 | 0 | 13 | 0 | 2 | 90% |
KOKAN REGION | KALYAN ZONE | PALGHAR (MINI) CIRCLE | PALGHAR DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 7 | 4 | 22 | 5 | 14 | 22 | 15 | 57% |
KOKAN REGION | KALYAN ZONE | VASAI CIRCLE | VASAI DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 1792 | 1669 | 128 | 0 | 18 | 5 | 13 | 93% |
KOKAN REGION | KALYAN ZONE | VASAI CIRCLE | VASAI DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Urban | 7 | 11006 | 10535 | 122 | 0 | 6 | 1 | 4 | 96% |
KOKAN REGION | KALYAN ZONE | VASAI CIRCLE | VASAI DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 138 | 70 | 96 | 0 | 9 | 0 | 0 | 51% |
KOKAN REGION | KALYAN ZONE | VASAI CIRCLE | VASAI DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Urban | 90 | 381 | 271 | 101 | 1 | 28 | 5 | 18 | 71% |
KOKAN REGION | KALYAN ZONE | VASAI CIRCLE | VASAI DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 24 | 24 | 95 | 0 | 32 | 0 | 24 | 100% |
KOKAN REGION | KALYAN ZONE | VASAI CIRCLE | VASAI DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Urban | 7 | 98 | 87 | 48 | 0 | 5 | 1 | 2 | 89% |
KOKAN REGION | KALYAN ZONE | VASAI CIRCLE | VASAI DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 3 | 2 | 45 | 0 | 23 | 0 | 23 | 67% |
KOKAN REGION | KALYAN ZONE | VASAI CIRCLE | VASAI DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Urban | 90 | 7 | 6 | 47 | 0 | 20 | 0 | 14 | 86% |
KOKAN REGION | KALYAN ZONE | VASAI CIRCLE | VIRAR O DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Urban | 7 | 11781 | 11396 | 106 | 0 | 5 | 2 | 4 | 97% |
KOKAN REGION | KALYAN ZONE | VASAI CIRCLE | VIRAR O DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Urban | 90 | 528 | 424 | 98 | 0 | 10 | 2 | 3 | 80% |
KOKAN REGION | KALYAN ZONE | VASAI CIRCLE | VIRAR O DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Urban | 7 | 156 | 136 | 60 | 0 | 6 | 0 | 4 | 87% |
KOKAN REGION | KALYAN ZONE | VASAI CIRCLE | VIRAR O DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Urban | 90 | 3 | 2 | 26 | 2 | 14 | 2 | 14 | 67% |
KOKAN REGION | KOKAN ZONE,RATNAGIRI | RATNAGIRI CIRCLE | CHIPLUN DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 1594 | 1511 | 51 | 0 | 9 | 2 | 6 | 95% |
KOKAN REGION | KOKAN ZONE,RATNAGIRI | RATNAGIRI CIRCLE | CHIPLUN DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 608 | 351 | 162 | 1 | 19 | 2 | 10 | 58% |
KOKAN REGION | KOKAN ZONE,RATNAGIRI | RATNAGIRI CIRCLE | CHIPLUN DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 16 | 11 | 34 | 1 | 13 | 1 | 6 | 69% |
KOKAN REGION | KOKAN ZONE,RATNAGIRI | RATNAGIRI CIRCLE | CHIPLUN DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 4 | 3 | 99 | 4 | 42 | 4 | 22 | 75% |
KOKAN REGION | KOKAN ZONE,RATNAGIRI | RATNAGIRI CIRCLE | KHED DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 1803 | 1716 | 75 | 0 | 8 | 2 | 5 | 95% |
KOKAN REGION | KOKAN ZONE,RATNAGIRI | RATNAGIRI CIRCLE | KHED DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 349 | 174 | 143 | 1 | 22 | 10 | 14 | 50% |
KOKAN REGION | KOKAN ZONE,RATNAGIRI | RATNAGIRI CIRCLE | KHED DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 53 | 48 | 59 | 1 | 15 | 2 | 12 | 91% |
KOKAN REGION | KOKAN ZONE,RATNAGIRI | RATNAGIRI CIRCLE | KHED DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 2 | 1 | 19 | 19 | 19 | 19 | 19 | 50% |
KOKAN REGION | KOKAN ZONE,RATNAGIRI | RATNAGIRI CIRCLE | RATNAGARI DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 2977 | 2862 | 78 | 0 | 8 | 3 | 6 | 96% |
KOKAN REGION | KOKAN ZONE,RATNAGIRI | RATNAGIRI CIRCLE | RATNAGARI DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 383 | 187 | 152 | 0 | 53 | 86 | 40 | 49% |
KOKAN REGION | KOKAN ZONE,RATNAGIRI | RATNAGIRI CIRCLE | RATNAGARI DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 153 | 141 | 109 | 0 | 12 | 0 | 6 | 92% |
KOKAN REGION | KOKAN ZONE,RATNAGIRI | RATNAGIRI CIRCLE | RATNAGARI DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 11 | 5 | 33 | 0 | 15 | 0 | 8 | 45% |
KOKAN REGION | KOKAN ZONE,RATNAGIRI | SINDUDURG CIRCLE | KANKAVALI DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 1968 | 1841 | 84 | 0 | 9 | 2 | 6 | 94% |
KOKAN REGION | KOKAN ZONE,RATNAGIRI | SINDUDURG CIRCLE | KANKAVALI DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 242 | 154 | 144 | 0 | 37 | 27 | 27 | 64% |
KOKAN REGION | KOKAN ZONE,RATNAGIRI | SINDUDURG CIRCLE | KANKAVALI DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 81 | 73 | 124 | 0 | 20 | 0 | 9 | 90% |
KOKAN REGION | KOKAN ZONE,RATNAGIRI | SINDUDURG CIRCLE | KANKAVALI DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 9 | 4 | 43 | 0 | 14 | 0 | 7 | 44% |
KOKAN REGION | KOKAN ZONE,RATNAGIRI | SINDUDURG CIRCLE | KUDAL DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 1741 | 1678 | 122 | 0 | 15 | 1 | 10 | 96% |
KOKAN REGION | KOKAN ZONE,RATNAGIRI | SINDUDURG CIRCLE | KUDAL DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 268 | 205 | 124 | 2 | 41 | 26 | 33 | 76% |
KOKAN REGION | KOKAN ZONE,RATNAGIRI | SINDUDURG CIRCLE | KUDAL DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 107 | 91 | 85 | 0 | 17 | 3 | 13 | 85% |
KOKAN REGION | KOKAN ZONE,RATNAGIRI | SINDUDURG CIRCLE | KUDAL DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 11 | 10 | 59 | 0 | 26 | 34 | 34 | 91% |
KOKAN REGION | NASIK ZONE | AHILYANAGAR CIRCLE | AHILYANAGAR RURAL DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 2317 | 2113 | 136 | 0 | 11 | 7 | 8 | 91% |
KOKAN REGION | NASIK ZONE | AHILYANAGAR CIRCLE | AHILYANAGAR RURAL DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 140 | 113 | 119 | 0 | 50 | 86 | 37 | 81% |
KOKAN REGION | NASIK ZONE | AHILYANAGAR CIRCLE | AHILYANAGAR RURAL DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 6 | 5 | 24 | 3 | 11 | 3 | 7 | 83% |
KOKAN REGION | NASIK ZONE | AHILYANAGAR CIRCLE | AHILYANAGAR RURAL DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 1 | 1 | 26 | 26 | 26 | 26 | 26 | 100% |
KOKAN REGION | NASIK ZONE | AHILYANAGAR CIRCLE | AHILYANAGAR URBAN DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 1575 | 1545 | 79 | 0 | 9 | 0 | 6 | 98% |
KOKAN REGION | NASIK ZONE | AHILYANAGAR CIRCLE | AHILYANAGAR URBAN DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Urban | 7 | 3170 | 3148 | 139 | 0 | 10 | 1 | 7 | 99% |
KOKAN REGION | NASIK ZONE | AHILYANAGAR CIRCLE | AHILYANAGAR URBAN DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 265 | 182 | 137 | 0 | 28 | 32 | 23 | 69% |
KOKAN REGION | NASIK ZONE | AHILYANAGAR CIRCLE | AHILYANAGAR URBAN DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Urban | 90 | 85 | 54 | 134 | 0 | 29 | 12 | 21 | 64% |
KOKAN REGION | NASIK ZONE | AHILYANAGAR CIRCLE | AHILYANAGAR URBAN DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 7 | 7 | 30 | 0 | 10 | 0 | 10 | 100% |
KOKAN REGION | NASIK ZONE | AHILYANAGAR CIRCLE | AHILYANAGAR URBAN DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Urban | 7 | 31 | 21 | 34 | 0 | 5 | 1 | 1 | 68% |
KOKAN REGION | NASIK ZONE | AHILYANAGAR CIRCLE | AHILYANAGAR URBAN DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 7 | 6 | 42 | 0 | 17 | 0 | 13 | 86% |
KOKAN REGION | NASIK ZONE | AHILYANAGAR CIRCLE | KARJAT (R) DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 1997 | 1913 | 73 | 0 | 6 | 0 | 3 | 96% |
KOKAN REGION | NASIK ZONE | AHILYANAGAR CIRCLE | KARJAT (R) DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 215 | 174 | 165 | 0 | 29 | 17 | 17 | 81% |
KOKAN REGION | NASIK ZONE | AHILYANAGAR CIRCLE | KARJAT (R) DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 4 | 4 | 4 | 0 | 1 | 0 | 0 | 100% |
KOKAN REGION | NASIK ZONE | AHILYANAGAR CIRCLE | KARJAT (R) DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 1 | 0 | 0 | 0 | 0 | 0 | 0 | 0% |
KOKAN REGION | NASIK ZONE | AHILYANAGAR CIRCLE | SANGEMNER DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 3963 | 3874 | 119 | 0 | 7 | 0 | 5 | 98% |
KOKAN REGION | NASIK ZONE | AHILYANAGAR CIRCLE | SANGEMNER DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 586 | 530 | 93 | 0 | 12 | 0 | 7 | 90% |
KOKAN REGION | NASIK ZONE | AHILYANAGAR CIRCLE | SANGEMNER DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 33 | 33 | 29 | 0 | 3 | 0 | 2 | 100% |
KOKAN REGION | NASIK ZONE | AHILYANAGAR CIRCLE | SANGEMNER DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 2 | 2 | 5 | 3 | 4 | 3 | 4 | 100% |
KOKAN REGION | NASIK ZONE | AHILYANAGAR CIRCLE | SHRIRAMPUR RURAL DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 2295 | 2258 | 118 | 0 | 6 | 1 | 4 | 98% |
KOKAN REGION | NASIK ZONE | AHILYANAGAR CIRCLE | SHRIRAMPUR RURAL DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 147 | 125 | 84 | 0 | 16 | 1 | 8 | 85% |
KOKAN REGION | NASIK ZONE | AHILYANAGAR CIRCLE | SHRIRAMPUR RURAL DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 8 | 7 | 20 | 0 | 3 | 0 | 0 | 88% |
KOKAN REGION | NASIK ZONE | MALEGAON CIRCLE | KALWAN DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 1291 | 1247 | 131 | 0 | 5 | 1 | 3 | 97% |
KOKAN REGION | NASIK ZONE | MALEGAON CIRCLE | KALWAN DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 74 | 51 | 137 | 0 | 13 | 1 | 2 | 69% |
KOKAN REGION | NASIK ZONE | MALEGAON CIRCLE | KALWAN DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 38 | 35 | 7 | 0 | 2 | 2 | 2 | 92% |
KOKAN REGION | NASIK ZONE | MALEGAON CIRCLE | MALEGAON URBAN DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 1122 | 1001 | 73 | 0 | 15 | 7 | 13 | 89% |
KOKAN REGION | NASIK ZONE | MALEGAON CIRCLE | MALEGAON URBAN DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 78 | 45 | 124 | 1 | 30 | 26 | 25 | 58% |
KOKAN REGION | NASIK ZONE | MALEGAON CIRCLE | MALEGAON URBAN DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 5 | 5 | 34 | 6 | 20 | 6 | 14 | 100% |
KOKAN REGION | NASIK ZONE | MALEGAON CIRCLE | MANMAD RURAL DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 1482 | 1403 | 138 | 0 | 15 | 6 | 12 | 95% |
KOKAN REGION | NASIK ZONE | MALEGAON CIRCLE | MANMAD RURAL DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 45 | 26 | 86 | 5 | 29 | 6 | 22 | 58% |
KOKAN REGION | NASIK ZONE | MALEGAON CIRCLE | MANMAD RURAL DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 6 | 6 | 8 | 1 | 3 | 1 | 2 | 100% |
KOKAN REGION | NASIK ZONE | MALEGAON CIRCLE | SATANA DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 932 | 917 | 56 | 0 | 10 | 0 | 8 | 98% |
KOKAN REGION | NASIK ZONE | MALEGAON CIRCLE | SATANA DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 89 | 73 | 90 | 0 | 15 | 0 | 2 | 82% |
KOKAN REGION | NASIK ZONE | MALEGAON CIRCLE | SATANA DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 5 | 5 | 13 | 1 | 7 | 13 | 5 | 100% |
KOKAN REGION | NASIK ZONE | NASHIK CIRCLE | CHANDWAD DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 1773 | 1687 | 45 | 0 | 6 | 2 | 5 | 95% |
KOKAN REGION | NASIK ZONE | NASHIK CIRCLE | CHANDWAD DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 163 | 136 | 139 | 0 | 39 | 56 | 34 | 83% |
KOKAN REGION | NASIK ZONE | NASHIK CIRCLE | CHANDWAD DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 32 | 30 | 15 | 0 | 4 | 0 | 2 | 94% |
KOKAN REGION | NASIK ZONE | NASHIK CIRCLE | CHANDWAD DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 1 | 1 | 61 | 61 | 61 | 61 | 61 | 100% |
KOKAN REGION | NASIK ZONE | NASHIK CIRCLE | NASIK RURAL DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 3710 | 3616 | 99 | 0 | 6 | 1 | 4 | 97% |
KOKAN REGION | NASIK ZONE | NASHIK CIRCLE | NASIK RURAL DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 901 | 687 | 137 | 0 | 22 | 8 | 14 | 76% |
KOKAN REGION | NASIK ZONE | NASHIK CIRCLE | NASIK RURAL DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 37 | 34 | 16 | 0 | 5 | 1 | 3 | 92% |
KOKAN REGION | NASIK ZONE | NASHIK CIRCLE | NASIK RURAL DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 2 | 2 | 73 | 19 | 46 | 19 | 46 | 100% |
KOKAN REGION | NASIK ZONE | NASHIK CIRCLE | NASIK URBAN DN. I | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Metro | 3 | 3604 | 3562 | 23 | 0 | 1 | 0 | 0 | 99% |
KOKAN REGION | NASIK ZONE | NASHIK CIRCLE | NASIK URBAN DN. I | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Metro | 90 | 287 | 266 | 103 | 0 | 9 | 0 | 0 | 93% |
KOKAN REGION | NASIK ZONE | NASHIK CIRCLE | NASIK URBAN DN. I | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Metro | 3 | 62 | 56 | 5 | 0 | 0 | 0 | 0 | 90% |
KOKAN REGION | NASIK ZONE | NASHIK CIRCLE | NASIK URBAN DN. I | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Metro | 90 | 1 | 1 | 4 | 4 | 4 | 4 | 4 | 100% |
KOKAN REGION | NASIK ZONE | NASHIK CIRCLE | NASIK URBAN DN. II | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Metro | 3 | 8567 | 8314 | 33 | 0 | 2 | 1 | 1 | 97% |
KOKAN REGION | NASIK ZONE | NASHIK CIRCLE | NASIK URBAN DN. II | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 3318 | 3202 | 67 | 0 | 5 | 3 | 4 | 97% |
KOKAN REGION | NASIK ZONE | NASHIK CIRCLE | NASIK URBAN DN. II | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Metro | 90 | 883 | 762 | 87 | 0 | 8 | 1 | 2 | 86% |
KOKAN REGION | NASIK ZONE | NASHIK CIRCLE | NASIK URBAN DN. II | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 745 | 652 | 137 | 0 | 12 | 4 | 9 | 88% |
KOKAN REGION | NASIK ZONE | NASHIK CIRCLE | NASIK URBAN DN. II | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Metro | 3 | 56 | 49 | 3 | 0 | 1 | 0 | 1 | 88% |
KOKAN REGION | NASIK ZONE | NASHIK CIRCLE | NASIK URBAN DN. II | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 29 | 27 | 9 | 0 | 2 | 1 | 1 | 93% |
KOKAN REGION | NASIK ZONE | NASHIK CIRCLE | NASIK URBAN DN. II | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Metro | 90 | 3 | 2 | 6 | 3 | 5 | 3 | 5 | 67% |
KOKAN REGION | NASIK ZONE | NASHIK CIRCLE | NASIK URBAN DN. II | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 8 | 7 | 52 | 2 | 11 | 2 | 3 | 88% |
NAGPUR REGION | AKOLA ZONE | AKOLA CIRCLE | AKOLA RURAL DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 2202 | 2123 | 135 | 0 | 23 | 7 | 17 | 96% |
NAGPUR REGION | AKOLA ZONE | AKOLA CIRCLE | AKOLA RURAL DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 143 | 45 | 131 | 0 | 60 | 119 | 52 | 31% |
NAGPUR REGION | AKOLA ZONE | AKOLA CIRCLE | AKOLA RURAL DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 13 | 12 | 60 | 1 | 20 | 1 | 18 | 92% |
NAGPUR REGION | AKOLA ZONE | AKOLA CIRCLE | AKOLA RURAL DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 1 | 1 | 37 | 37 | 37 | 37 | 37 | 100% |
NAGPUR REGION | AKOLA ZONE | AKOLA CIRCLE | AKOLA URBAN DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Urban | 7 | 1654 | 1627 | 109 | 0 | 17 | 6 | 11 | 98% |
NAGPUR REGION | AKOLA ZONE | AKOLA CIRCLE | AKOLA URBAN DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Urban | 90 | 330 | 95 | 159 | 0 | 52 | 21 | 43 | 29% |
NAGPUR REGION | AKOLA ZONE | AKOLA CIRCLE | AKOLA URBAN DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Urban | 7 | 52 | 44 | 124 | 0 | 5 | 0 | 2 | 85% |
NAGPUR REGION | AKOLA ZONE | AKOLA CIRCLE | AKOT DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 1342 | 1299 | 154 | 0 | 18 | 6 | 12 | 97% |
NAGPUR REGION | AKOLA ZONE | AKOLA CIRCLE | AKOT DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 90 | 46 | 141 | 2 | 62 | 69 | 69 | 51% |
NAGPUR REGION | AKOLA ZONE | AKOLA CIRCLE | AKOT DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 5 | 4 | 28 | 3 | 10 | 3 | 5 | 80% |
NAGPUR REGION | AKOLA ZONE | BULDHANA CIRCLE | BULDHANA DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 2183 | 2153 | 159 | 0 | 12 | 0 | 7 | 99% |
NAGPUR REGION | AKOLA ZONE | BULDHANA CIRCLE | BULDHANA DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 161 | 123 | 98 | 0 | 31 | 0 | 24 | 76% |
NAGPUR REGION | AKOLA ZONE | BULDHANA CIRCLE | BULDHANA DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 13 | 11 | 27 | 0 | 4 | 0 | 1 | 85% |
NAGPUR REGION | AKOLA ZONE | BULDHANA CIRCLE | KHAMGAON CONSTRUCTION DIV | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 1692 | 1654 | 141 | 0 | 18 | 0 | 11 | 98% |
NAGPUR REGION | AKOLA ZONE | BULDHANA CIRCLE | KHAMGAON CONSTRUCTION DIV | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 259 | 162 | 165 | 0 | 41 | 106 | 29 | 63% |
NAGPUR REGION | AKOLA ZONE | BULDHANA CIRCLE | KHAMGAON CONSTRUCTION DIV | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 32 | 23 | 7 | 0 | 2 | 0 | 1 | 72% |
NAGPUR REGION | AKOLA ZONE | BULDHANA CIRCLE | KHAMGAON CONSTRUCTION DIV | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 1 | 1 | 17 | 17 | 17 | 17 | 17 | 100% |
NAGPUR REGION | AKOLA ZONE | BULDHANA CIRCLE | MALKAPUR DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 1892 | 1833 | 127 | 0 | 20 | 3 | 15 | 97% |
NAGPUR REGION | AKOLA ZONE | BULDHANA CIRCLE | MALKAPUR DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 117 | 72 | 143 | 5 | 52 | 20 | 40 | 62% |
NAGPUR REGION | AKOLA ZONE | BULDHANA CIRCLE | MALKAPUR DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 7 | 6 | 6 | 0 | 2 | 0 | 1 | 86% |
NAGPUR REGION | AKOLA ZONE | BULDHANA CIRCLE | Mehkar Division | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 2367 | 2004 | 140 | 0 | 18 | 0 | 12 | 85% |
NAGPUR REGION | AKOLA ZONE | BULDHANA CIRCLE | Mehkar Division | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 260 | 64 | 93 | 0 | 25 | 5 | 9 | 25% |
NAGPUR REGION | AKOLA ZONE | BULDHANA CIRCLE | Mehkar Division | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 4 | 4 | 26 | 18 | 23 | 18 | 24 | 100% |
NAGPUR REGION | AKOLA ZONE | BULDHANA CIRCLE | Mehkar Division | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 1 | 1 | 0 | 0 | 0 | 0 | 0 | 100% |
NAGPUR REGION | AKOLA ZONE | WASHIM CIRCLE | WASHIM DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 3055 | 2924 | 158 | 0 | 25 | 5 | 20 | 96% |
NAGPUR REGION | AKOLA ZONE | WASHIM CIRCLE | WASHIM DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 104 | 47 | 128 | 0 | 41 | 18 | 31 | 45% |
NAGPUR REGION | AKOLA ZONE | WASHIM CIRCLE | WASHIM DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 6 | 6 | 60 | 0 | 19 | 0 | 13 | 100% |
NAGPUR REGION | AMARAVATI ZONE | AMARAVATI CIRCLE | ACHALPUR DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 3479 | 3401 | 161 | 0 | 12 | 6 | 8 | 98% |
NAGPUR REGION | AMARAVATI ZONE | AMARAVATI CIRCLE | ACHALPUR DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 132 | 96 | 157 | 0 | 63 | 109 | 58 | 73% |
NAGPUR REGION | AMARAVATI ZONE | AMARAVATI CIRCLE | ACHALPUR DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 29 | 29 | 59 | 1 | 7 | 2 | 4 | 100% |
NAGPUR REGION | AMARAVATI ZONE | AMARAVATI CIRCLE | AMARAVATI CONSTRUCTION DN | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 1964 | 1899 | 132 | 0 | 10 | 0 | 6 | 97% |
NAGPUR REGION | AMARAVATI ZONE | AMARAVATI CIRCLE | AMARAVATI CONSTRUCTION DN | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 210 | 117 | 117 | 0 | 31 | 0 | 21 | 56% |
NAGPUR REGION | AMARAVATI ZONE | AMARAVATI CIRCLE | AMARAVATI CONSTRUCTION DN | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 11 | 7 | 5 | 0 | 2 | 1 | 1 | 64% |
NAGPUR REGION | AMARAVATI ZONE | AMARAVATI CIRCLE | AMARAVATI CONSTRUCTION DN | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 2 | 2 | 10 | 0 | 5 | 0 | 5 | 100% |
NAGPUR REGION | AMARAVATI ZONE | AMARAVATI CIRCLE | AMARAVATI URBAN DIVSION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Metro | 3 | 2869 | 2800 | 134 | 0 | 10 | 0 | 6 | 98% |
NAGPUR REGION | AMARAVATI ZONE | AMARAVATI CIRCLE | AMARAVATI URBAN DIVSION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Metro | 90 | 209 | 85 | 76 | 0 | 22 | 8 | 10 | 41% |
NAGPUR REGION | AMARAVATI ZONE | AMARAVATI CIRCLE | AMARAVATI URBAN DIVSION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Metro | 3 | 40 | 29 | 31 | 0 | 4 | 0 | 1 | 73% |
NAGPUR REGION | AMARAVATI ZONE | AMARAVATI CIRCLE | AMARAVATI URBAN DIVSION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Metro | 90 | 2 | 2 | 19 | 18 | 19 | 18 | 19 | 100% |
NAGPUR REGION | AMARAVATI ZONE | AMARAVATI CIRCLE | MORSHI DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 1491 | 1458 | 66 | 0 | 8 | 2 | 5 | 98% |
NAGPUR REGION | AMARAVATI ZONE | AMARAVATI CIRCLE | MORSHI DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 108 | 83 | 128 | 0 | 39 | 11 | 32 | 77% |
NAGPUR REGION | AMARAVATI ZONE | AMARAVATI CIRCLE | MORSHI DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 11 | 11 | 10 | 0 | 2 | 2 | 2 | 100% |
NAGPUR REGION | AMARAVATI ZONE | YAVATMAL CIRCLE | Darvha Division | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 2383 | 2312 | 111 | 0 | 11 | 5 | 8 | 97% |
NAGPUR REGION | AMARAVATI ZONE | YAVATMAL CIRCLE | Darvha Division | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 81 | 51 | 151 | 0 | 41 | 12 | 38 | 63% |
NAGPUR REGION | AMARAVATI ZONE | YAVATMAL CIRCLE | Darvha Division | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 3 | 3 | 6 | 1 | 3 | 1 | 1 | 100% |
NAGPUR REGION | AMARAVATI ZONE | YAVATMAL CIRCLE | Darvha Division | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 2 | 2 | 51 | 21 | 36 | 21 | 36 | 100% |
NAGPUR REGION | AMARAVATI ZONE | YAVATMAL CIRCLE | PANDHARKAWADA DN. | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 2003 | 1962 | 104 | 0 | 13 | 6 | 10 | 98% |
NAGPUR REGION | AMARAVATI ZONE | YAVATMAL CIRCLE | PANDHARKAWADA DN. | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 71 | 30 | 87 | 0 | 36 | 47 | 35 | 42% |
NAGPUR REGION | AMARAVATI ZONE | YAVATMAL CIRCLE | PANDHARKAWADA DN. | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 18 | 13 | 28 | 1 | 12 | 1 | 13 | 72% |
NAGPUR REGION | AMARAVATI ZONE | YAVATMAL CIRCLE | PANDHARKAWADA DN. | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 1 | 1 | 3 | 3 | 3 | 3 | 3 | 100% |
NAGPUR REGION | AMARAVATI ZONE | YAVATMAL CIRCLE | PUSAD DIVSION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 2466 | 2343 | 131 | 0 | 16 | 15 | 15 | 95% |
NAGPUR REGION | AMARAVATI ZONE | YAVATMAL CIRCLE | PUSAD DIVSION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 99 | 73 | 132 | 0 | 39 | 25 | 32 | 74% |
NAGPUR REGION | AMARAVATI ZONE | YAVATMAL CIRCLE | PUSAD DIVSION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 12 | 12 | 49 | 0 | 15 | 16 | 13 | 100% |
NAGPUR REGION | AMARAVATI ZONE | YAVATMAL CIRCLE | YAVATMAL DIVSION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 1384 | 1358 | 139 | 0 | 13 | 1 | 7 | 98% |
NAGPUR REGION | AMARAVATI ZONE | YAVATMAL CIRCLE | YAVATMAL DIVSION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 116 | 87 | 128 | 0 | 22 | 28 | 17 | 75% |
NAGPUR REGION | AMARAVATI ZONE | YAVATMAL CIRCLE | YAVATMAL DIVSION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 25 | 19 | 14 | 0 | 3 | 1 | 1 | 76% |
NAGPUR REGION | CHANDRAPUR ZONE | CHANDRAPUR CIRCLE | BALLARSHAH DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 2410 | 2320 | 91 | 0 | 11 | 7 | 10 | 96% |
NAGPUR REGION | CHANDRAPUR ZONE | CHANDRAPUR CIRCLE | BALLARSHAH DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 150 | 102 | 105 | 0 | 27 | 12 | 13 | 68% |
NAGPUR REGION | CHANDRAPUR ZONE | CHANDRAPUR CIRCLE | BALLARSHAH DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 36 | 28 | 27 | 0 | 6 | 0 | 4 | 78% |
NAGPUR REGION | CHANDRAPUR ZONE | CHANDRAPUR CIRCLE | BALLARSHAH DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 1 | 1 | 30 | 30 | 30 | 30 | 30 | 100% |
NAGPUR REGION | CHANDRAPUR ZONE | CHANDRAPUR CIRCLE | CHANDRAPUR DIVSION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 1009 | 977 | 86 | 0 | 11 | 2 | 9 | 97% |
NAGPUR REGION | CHANDRAPUR ZONE | CHANDRAPUR CIRCLE | CHANDRAPUR DIVSION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Urban | 7 | 1118 | 1071 | 76 | 0 | 9 | 4 | 7 | 96% |
NAGPUR REGION | CHANDRAPUR ZONE | CHANDRAPUR CIRCLE | CHANDRAPUR DIVSION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 40 | 14 | 90 | 6 | 43 | 55 | 42 | 35% |
NAGPUR REGION | CHANDRAPUR ZONE | CHANDRAPUR CIRCLE | CHANDRAPUR DIVSION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Urban | 90 | 70 | 40 | 140 | 0 | 32 | 8 | 13 | 57% |
NAGPUR REGION | CHANDRAPUR ZONE | CHANDRAPUR CIRCLE | CHANDRAPUR DIVSION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 20 | 19 | 18 | 0 | 5 | 0 | 3 | 95% |
NAGPUR REGION | CHANDRAPUR ZONE | CHANDRAPUR CIRCLE | CHANDRAPUR DIVSION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Urban | 7 | 57 | 41 | 27 | 0 | 4 | 0 | 1 | 72% |
NAGPUR REGION | CHANDRAPUR ZONE | CHANDRAPUR CIRCLE | CHANDRAPUR DIVSION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Urban | 90 | 1 | 1 | 2 | 2 | 2 | 2 | 2 | 100% |
NAGPUR REGION | CHANDRAPUR ZONE | CHANDRAPUR CIRCLE | WARORA DIVSION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 1442 | 1393 | 117 | 0 | 12 | 9 | 10 | 97% |
NAGPUR REGION | CHANDRAPUR ZONE | CHANDRAPUR CIRCLE | WARORA DIVSION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 108 | 67 | 127 | 0 | 34 | 24 | 27 | 62% |
NAGPUR REGION | CHANDRAPUR ZONE | CHANDRAPUR CIRCLE | WARORA DIVSION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 15 | 15 | 47 | 1 | 8 | 2 | 4 | 100% |
NAGPUR REGION | CHANDRAPUR ZONE | CHANDRAPUR CIRCLE | WARORA DIVSION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 3 | 2 | 93 | 47 | 70 | 47 | 70 | 67% |
NAGPUR REGION | CHANDRAPUR ZONE | GADCHIROLI CIRCLE | ALLAPALLI DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 2437 | 2250 | 104 | 0 | 14 | 5 | 12 | 92% |
NAGPUR REGION | CHANDRAPUR ZONE | GADCHIROLI CIRCLE | ALLAPALLI DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 66 | 37 | 74 | 0 | 18 | 0 | 13 | 56% |
NAGPUR REGION | CHANDRAPUR ZONE | GADCHIROLI CIRCLE | ALLAPALLI DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 15 | 15 | 65 | 1 | 12 | 7 | 7 | 100% |
NAGPUR REGION | CHANDRAPUR ZONE | GADCHIROLI CIRCLE | ALLAPALLI DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 1 | 1 | 52 | 52 | 52 | 52 | 52 | 100% |
NAGPUR REGION | CHANDRAPUR ZONE | GADCHIROLI CIRCLE | BRAMHAPURI DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 1375 | 1357 | 59 | 0 | 3 | 1 | 2 | 99% |
NAGPUR REGION | CHANDRAPUR ZONE | GADCHIROLI CIRCLE | BRAMHAPURI DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 98 | 77 | 119 | 0 | 23 | 2 | 12 | 79% |
NAGPUR REGION | CHANDRAPUR ZONE | GADCHIROLI CIRCLE | BRAMHAPURI DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 49 | 47 | 14 | 0 | 2 | 1 | 2 | 96% |
NAGPUR REGION | CHANDRAPUR ZONE | GADCHIROLI CIRCLE | BRAMHAPURI DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 6 | 4 | 3 | 1 | 2 | 3 | 3 | 67% |
NAGPUR REGION | CHANDRAPUR ZONE | GADCHIROLI CIRCLE | GADCHIROLI DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 2288 | 2199 | 113 | 0 | 9 | 7 | 7 | 96% |
NAGPUR REGION | CHANDRAPUR ZONE | GADCHIROLI CIRCLE | GADCHIROLI DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 56 | 37 | 82 | 0 | 31 | 2 | 33 | 66% |
NAGPUR REGION | CHANDRAPUR ZONE | GADCHIROLI CIRCLE | GADCHIROLI DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 182 | 157 | 59 | 0 | 13 | 6 | 10 | 86% |
NAGPUR REGION | CHANDRAPUR ZONE | GADCHIROLI CIRCLE | GADCHIROLI DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 11 | 9 | 44 | 1 | 19 | 1 | 18 | 82% |
NAGPUR REGION | GONDIA ZONE | BHANDARA CIRCLE | BHANDARA DIVSION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 2587 | 2501 | 126 | 0 | 11 | 1 | 7 | 97% |
NAGPUR REGION | GONDIA ZONE | BHANDARA CIRCLE | BHANDARA DIVSION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 161 | 95 | 124 | 0 | 44 | 0 | 38 | 59% |
NAGPUR REGION | GONDIA ZONE | BHANDARA CIRCLE | BHANDARA DIVSION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 56 | 42 | 18 | 0 | 4 | 0 | 2 | 75% |
NAGPUR REGION | GONDIA ZONE | BHANDARA CIRCLE | SAKOLI O DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 957 | 937 | 33 | 0 | 5 | 1 | 4 | 98% |
NAGPUR REGION | GONDIA ZONE | BHANDARA CIRCLE | SAKOLI O DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 84 | 46 | 121 | 0 | 46 | 13 | 37 | 55% |
NAGPUR REGION | GONDIA ZONE | BHANDARA CIRCLE | SAKOLI O DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 12 | 12 | 24 | 0 | 3 | 2 | 2 | 100% |
NAGPUR REGION | GONDIA ZONE | BHANDARA CIRCLE | SAKOLI O DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 1 | 1 | 54 | 54 | 54 | 54 | 54 | 100% |
NAGPUR REGION | GONDIA ZONE | GONDIA CIRCLE | DEORI DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 1535 | 1448 | 70 | 0 | 13 | 2 | 9 | 94% |
NAGPUR REGION | GONDIA ZONE | GONDIA CIRCLE | DEORI DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 227 | 185 | 148 | 0 | 28 | 14 | 14 | 81% |
NAGPUR REGION | GONDIA ZONE | GONDIA CIRCLE | DEORI DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 25 | 20 | 14 | 0 | 3 | 1 | 1 | 80% |
NAGPUR REGION | GONDIA ZONE | GONDIA CIRCLE | GONDIA DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 2633 | 2530 | 106 | 0 | 11 | 4 | 8 | 96% |
NAGPUR REGION | GONDIA ZONE | GONDIA CIRCLE | GONDIA DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 111 | 66 | 147 | 1 | 48 | 1 | 37 | 59% |
NAGPUR REGION | GONDIA ZONE | GONDIA CIRCLE | GONDIA DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 51 | 38 | 41 | 0 | 5 | 1 | 1 | 75% |
NAGPUR REGION | NAGPUR ZONE | NAGPUR (R) CIRCLE | KATOL DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 961 | 930 | 94 | 0 | 5 | 1 | 4 | 97% |
NAGPUR REGION | NAGPUR ZONE | NAGPUR (R) CIRCLE | KATOL DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 66 | 49 | 117 | 0 | 25 | 1 | 12 | 74% |
NAGPUR REGION | NAGPUR ZONE | NAGPUR (R) CIRCLE | KATOL DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 19 | 10 | 19 | 0 | 3 | 0 | 1 | 53% |
NAGPUR REGION | NAGPUR ZONE | NAGPUR (R) CIRCLE | MOUDA DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 3995 | 3908 | 91 | 0 | 7 | 0 | 6 | 98% |
NAGPUR REGION | NAGPUR ZONE | NAGPUR (R) CIRCLE | MOUDA DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 87 | 35 | 153 | 1 | 47 | 41 | 41 | 40% |
NAGPUR REGION | NAGPUR ZONE | NAGPUR (R) CIRCLE | MOUDA DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 31 | 27 | 42 | 0 | 9 | 0 | 7 | 87% |
NAGPUR REGION | NAGPUR ZONE | NAGPUR (R) CIRCLE | MOUDA DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 11 | 7 | 91 | 37 | 52 | 42 | 42 | 64% |
NAGPUR REGION | NAGPUR ZONE | NAGPUR (R) CIRCLE | SAONER DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 1619 | 1561 | 47 | 0 | 6 | 1 | 5 | 96% |
NAGPUR REGION | NAGPUR ZONE | NAGPUR (R) CIRCLE | SAONER DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 123 | 83 | 148 | 0 | 27 | 6 | 15 | 67% |
NAGPUR REGION | NAGPUR ZONE | NAGPUR (R) CIRCLE | SAONER DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 45 | 42 | 13 | 0 | 3 | 0 | 2 | 93% |
NAGPUR REGION | NAGPUR ZONE | NAGPUR (R) CIRCLE | SAONER DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 2 | 2 | 19 | 9 | 14 | 9 | 14 | 100% |
NAGPUR REGION | NAGPUR ZONE | NAGPUR (R) CIRCLE | UMRED DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 1589 | 1560 | 23 | 0 | 3 | 1 | 2 | 98% |
NAGPUR REGION | NAGPUR ZONE | NAGPUR (R) CIRCLE | UMRED DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 61 | 31 | 113 | 0 | 51 | 37 | 48 | 51% |
NAGPUR REGION | NAGPUR ZONE | NAGPUR (R) CIRCLE | UMRED DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 60 | 58 | 25 | 0 | 3 | 1 | 1 | 97% |
NAGPUR REGION | NAGPUR ZONE | NAGPUR (R) CIRCLE | UMRED DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 1 | 0 | 0 | 0 | 0 | 0 | 0 | 0% |
NAGPUR REGION | NAGPUR ZONE | NAGPUR (U) CIRCLE | MIDC METER NAGPUR | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Metro | 3 | 380 | 374 | 8 | 0 | 0 | 0 | 0 | 98% |
NAGPUR REGION | NAGPUR ZONE | NAGPUR (U) CIRCLE | MIDC METER NAGPUR | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 2615 | 2534 | 85 | 0 | 4 | 2 | 3 | 97% |
NAGPUR REGION | NAGPUR ZONE | NAGPUR (U) CIRCLE | MIDC METER NAGPUR | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Metro | 90 | 175 | 150 | 121 | 0 | 12 | 7 | 7 | 86% |
NAGPUR REGION | NAGPUR ZONE | NAGPUR (U) CIRCLE | MIDC METER NAGPUR | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 178 | 143 | 111 | 0 | 12 | 11 | 6 | 80% |
NAGPUR REGION | NAGPUR ZONE | NAGPUR (U) CIRCLE | MIDC METER NAGPUR | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Metro | 3 | 5 | 4 | 2 | 0 | 1 | 0 | 0 | 80% |
NAGPUR REGION | NAGPUR ZONE | NAGPUR (U) CIRCLE | MIDC METER NAGPUR | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 56 | 48 | 38 | 0 | 3 | 1 | 2 | 86% |
NAGPUR REGION | NAGPUR ZONE | NAGPUR (U) CIRCLE | MIDC METER NAGPUR | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Metro | 90 | 3 | 1 | 0 | 0 | 0 | 0 | 0 | 33% |
NAGPUR REGION | NAGPUR ZONE | NAGPUR (U) CIRCLE | MIDC METER NAGPUR | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 11 | 7 | 45 | 0 | 14 | 0 | 2 | 64% |
NAGPUR REGION | NAGPUR ZONE | NAGPUR (U) CIRCLE | NAGPUR CIVIL LINES DIVN. | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Metro | 3 | 1892 | 1864 | 118 | 0 | 2 | 1 | 1 | 99% |
NAGPUR REGION | NAGPUR ZONE | NAGPUR (U) CIRCLE | NAGPUR CIVIL LINES DIVN. | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Metro | 90 | 1328 | 1256 | 57 | 0 | 2 | 2 | 1 | 95% |
NAGPUR REGION | NAGPUR ZONE | NAGPUR (U) CIRCLE | NAGPUR CIVIL LINES DIVN. | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Metro | 3 | 32 | 32 | 18 | 0 | 2 | 1 | 1 | 100% |
NAGPUR REGION | NAGPUR ZONE | NAGPUR (U) CIRCLE | NAGPUR CIVIL LINES DIVN. | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Metro | 90 | 19 | 12 | 5 | 0 | 1 | 0 | 0 | 63% |
NAGPUR REGION | NAGPUR ZONE | NAGPUR (U) CIRCLE | NAGPUR CONGRESS NAGAR DIV | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Metro | 3 | 1872 | 1845 | 56 | 0 | 1 | 0 | 1 | 99% |
NAGPUR REGION | NAGPUR ZONE | NAGPUR (U) CIRCLE | NAGPUR CONGRESS NAGAR DIV | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 3172 | 3081 | 91 | 0 | 4 | 1 | 3 | 97% |
NAGPUR REGION | NAGPUR ZONE | NAGPUR (U) CIRCLE | NAGPUR CONGRESS NAGAR DIV | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Metro | 90 | 102 | 60 | 81 | 0 | 12 | 1 | 3 | 59% |
NAGPUR REGION | NAGPUR ZONE | NAGPUR (U) CIRCLE | NAGPUR CONGRESS NAGAR DIV | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 140 | 106 | 56 | 0 | 15 | 18 | 10 | 76% |
NAGPUR REGION | NAGPUR ZONE | NAGPUR (U) CIRCLE | NAGPUR CONGRESS NAGAR DIV | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Metro | 3 | 75 | 63 | 15 | 0 | 1 | 0 | 0 | 84% |
NAGPUR REGION | NAGPUR ZONE | NAGPUR (U) CIRCLE | NAGPUR CONGRESS NAGAR DIV | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 19 | 18 | 6 | 0 | 2 | 0 | 2 | 95% |
NAGPUR REGION | NAGPUR ZONE | NAGPUR (U) CIRCLE | NAGPUR CONGRESS NAGAR DIV | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Metro | 90 | 1 | 0 | 0 | 0 | 0 | 0 | 0 | 0% |
NAGPUR REGION | NAGPUR ZONE | NAGPUR (U) CIRCLE | NAGPUR GANDHIBAUG DIV. | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Metro | 3 | 2444 | 2389 | 34 | 0 | 1 | 1 | 1 | 98% |
NAGPUR REGION | NAGPUR ZONE | NAGPUR (U) CIRCLE | NAGPUR GANDHIBAUG DIV. | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Metro | 90 | 30 | 14 | 106 | 0 | 37 | 7 | 15 | 47% |
NAGPUR REGION | NAGPUR ZONE | NAGPUR (U) CIRCLE | NAGPUR GANDHIBAUG DIV. | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Metro | 3 | 26 | 24 | 2 | 0 | 1 | 0 | 1 | 92% |
NAGPUR REGION | NAGPUR ZONE | NAGPUR (U) CIRCLE | NAGPUR MAHAL DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Metro | 3 | 2940 | 2887 | 79 | 0 | 2 | 1 | 1 | 98% |
NAGPUR REGION | NAGPUR ZONE | NAGPUR (U) CIRCLE | NAGPUR MAHAL DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Metro | 90 | 215 | 160 | 119 | 0 | 18 | 10 | 12 | 74% |
NAGPUR REGION | NAGPUR ZONE | NAGPUR (U) CIRCLE | NAGPUR MAHAL DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Metro | 3 | 55 | 46 | 27 | 0 | 2 | 0 | 1 | 84% |
NAGPUR REGION | NAGPUR ZONE | WARDHA CIRCLE | ARVI DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 893 | 884 | 98 | 0 | 6 | 1 | 4 | 99% |
NAGPUR REGION | NAGPUR ZONE | WARDHA CIRCLE | ARVI DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 94 | 61 | 105 | 0 | 37 | 23 | 29 | 65% |
NAGPUR REGION | NAGPUR ZONE | WARDHA CIRCLE | ARVI DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 16 | 15 | 16 | 0 | 4 | 0 | 2 | 94% |
NAGPUR REGION | NAGPUR ZONE | WARDHA CIRCLE | ARVI DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 2 | 1 | 1 | 1 | 1 | 1 | 1 | 50% |
NAGPUR REGION | NAGPUR ZONE | WARDHA CIRCLE | HINGANGHAT DIVSION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 1110 | 1083 | 34 | 0 | 5 | 2 | 4 | 98% |
NAGPUR REGION | NAGPUR ZONE | WARDHA CIRCLE | HINGANGHAT DIVSION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 56 | 32 | 124 | 3 | 40 | 56 | 39 | 57% |
NAGPUR REGION | NAGPUR ZONE | WARDHA CIRCLE | HINGANGHAT DIVSION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 7 | 7 | 17 | 0 | 8 | 0 | 8 | 100% |
NAGPUR REGION | NAGPUR ZONE | WARDHA CIRCLE | HINGANGHAT DIVSION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 1 | 1 | 16 | 16 | 16 | 16 | 16 | 100% |
NAGPUR REGION | NAGPUR ZONE | WARDHA CIRCLE | WARDHA DIVSION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 1815 | 1771 | 38 | 0 | 6 | 1 | 4 | 98% |
NAGPUR REGION | NAGPUR ZONE | WARDHA CIRCLE | WARDHA DIVSION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 143 | 91 | 140 | 0 | 26 | 0 | 17 | 64% |
NAGPUR REGION | NAGPUR ZONE | WARDHA CIRCLE | WARDHA DIVSION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 72 | 55 | 15 | 0 | 4 | 1 | 2 | 76% |
NAGPUR REGION | NAGPUR ZONE | WARDHA CIRCLE | WARDHA DIVSION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 2 | 2 | 115 | 13 | 64 | 13 | 64 | 100% |
PUNE REGION | BARAMATI ZONE | BARAMATI CIRCLE | BARAMATI DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 3000 | 2893 | 92 | 0 | 11 | 2 | 8 | 96% |
PUNE REGION | BARAMATI ZONE | BARAMATI CIRCLE | BARAMATI DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 1340 | 984 | 147 | 0 | 21 | 11 | 14 | 73% |
PUNE REGION | BARAMATI ZONE | BARAMATI CIRCLE | BARAMATI DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 10 | 9 | 60 | 0 | 17 | 0 | 2 | 90% |
PUNE REGION | BARAMATI ZONE | BARAMATI CIRCLE | BARAMATI DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 3 | 3 | 41 | 0 | 14 | 0 | 2 | 100% |
PUNE REGION | BARAMATI ZONE | BARAMATI CIRCLE | DOUND DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 3600 | 3441 | 126 | 0 | 12 | 7 | 10 | 96% |
PUNE REGION | BARAMATI ZONE | BARAMATI CIRCLE | DOUND DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 843 | 447 | 139 | 0 | 34 | 3 | 25 | 53% |
PUNE REGION | BARAMATI ZONE | BARAMATI CIRCLE | DOUND DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 21 | 21 | 35 | 0 | 11 | 5 | 9 | 100% |
PUNE REGION | BARAMATI ZONE | BARAMATI CIRCLE | DOUND DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 8 | 4 | 31 | 0 | 9 | 0 | 2 | 50% |
PUNE REGION | BARAMATI ZONE | BARAMATI CIRCLE | SASWAD DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 1179 | 1146 | 98 | 0 | 10 | 1 | 7 | 97% |
PUNE REGION | BARAMATI ZONE | BARAMATI CIRCLE | SASWAD DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 884 | 677 | 159 | 0 | 25 | 12 | 17 | 77% |
PUNE REGION | BARAMATI ZONE | BARAMATI CIRCLE | SASWAD DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 3 | 2 | 8 | 0 | 4 | 0 | 4 | 67% |
PUNE REGION | BARAMATI ZONE | BARAMATI CIRCLE | SASWAD DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 1 | 1 | 39 | 39 | 39 | 39 | 39 | 100% |
PUNE REGION | BARAMATI ZONE | SATARA CIRCLE | KARAD DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 2990 | 2863 | 66 | 0 | 8 | 2 | 6 | 96% |
PUNE REGION | BARAMATI ZONE | SATARA CIRCLE | KARAD DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 382 | 224 | 122 | 1 | 21 | 14 | 14 | 59% |
PUNE REGION | BARAMATI ZONE | SATARA CIRCLE | KARAD DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 19 | 19 | 33 | 0 | 4 | 1 | 1 | 100% |
PUNE REGION | BARAMATI ZONE | SATARA CIRCLE | KARAD DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 5 | 4 | 92 | 4 | 36 | 4 | 23 | 80% |
PUNE REGION | BARAMATI ZONE | SATARA CIRCLE | PHALTAN DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 2138 | 2047 | 81 | 0 | 6 | 1 | 4 | 96% |
PUNE REGION | BARAMATI ZONE | SATARA CIRCLE | PHALTAN DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 348 | 233 | 114 | 1 | 28 | 97 | 15 | 67% |
PUNE REGION | BARAMATI ZONE | SATARA CIRCLE | PHALTAN DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 25 | 21 | 7 | 0 | 1 | 0 | 0 | 84% |
PUNE REGION | BARAMATI ZONE | SATARA CIRCLE | PHALTAN DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 5 | 1 | 49 | 49 | 49 | 49 | 49 | 20% |
PUNE REGION | BARAMATI ZONE | SATARA CIRCLE | SATARA DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 2715 | 2643 | 106 | 0 | 8 | 2 | 5 | 97% |
PUNE REGION | BARAMATI ZONE | SATARA CIRCLE | SATARA DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 808 | 635 | 97 | 0 | 12 | 1 | 7 | 79% |
PUNE REGION | BARAMATI ZONE | SATARA CIRCLE | SATARA DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 49 | 44 | 22 | 0 | 3 | 0 | 1 | 90% |
PUNE REGION | BARAMATI ZONE | SATARA CIRCLE | SATARA DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 5 | 4 | 31 | 3 | 13 | 3 | 9 | 80% |
PUNE REGION | BARAMATI ZONE | SATARA CIRCLE | VADUJ DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 1904 | 1818 | 91 | 0 | 11 | 7 | 9 | 95% |
PUNE REGION | BARAMATI ZONE | SATARA CIRCLE | VADUJ DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 341 | 109 | 161 | 5 | 45 | 25 | 29 | 32% |
PUNE REGION | BARAMATI ZONE | SATARA CIRCLE | VADUJ DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 51 | 49 | 31 | 0 | 2 | 1 | 1 | 96% |
PUNE REGION | BARAMATI ZONE | SATARA CIRCLE | VADUJ DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 2 | 0 | 0 | 0 | 0 | 0 | 0 | 0% |
PUNE REGION | BARAMATI ZONE | SATARA CIRCLE | WAI DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 1355 | 1311 | 116 | 0 | 9 | 2 | 7 | 97% |
PUNE REGION | BARAMATI ZONE | SATARA CIRCLE | WAI DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 170 | 89 | 133 | 0 | 40 | 14 | 37 | 52% |
PUNE REGION | BARAMATI ZONE | SATARA CIRCLE | WAI DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 25 | 24 | 48 | 0 | 8 | 1 | 5 | 96% |
PUNE REGION | BARAMATI ZONE | SATARA CIRCLE | WAI DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 7 | 7 | 27 | 0 | 10 | 11 | 11 | 100% |
PUNE REGION | BARAMATI ZONE | SOLAPUR CIRCLE | AKLUJ O DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 1654 | 1557 | 59 | 0 | 5 | 2 | 3 | 94% |
PUNE REGION | BARAMATI ZONE | SOLAPUR CIRCLE | AKLUJ O DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 339 | 108 | 161 | 0 | 38 | 161 | 20 | 32% |
PUNE REGION | BARAMATI ZONE | SOLAPUR CIRCLE | AKLUJ O DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 3 | 3 | 5 | 0 | 2 | 0 | 1 | 100% |
PUNE REGION | BARAMATI ZONE | SOLAPUR CIRCLE | AKLUJ O DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 6 | 0 | 0 | 0 | 0 | 0 | 0 | 0% |
PUNE REGION | BARAMATI ZONE | SOLAPUR CIRCLE | BARSI DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 2813 | 2670 | 111 | 0 | 11 | 3 | 8 | 95% |
PUNE REGION | BARAMATI ZONE | SOLAPUR CIRCLE | BARSI DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 769 | 500 | 144 | 0 | 26 | 12 | 19 | 65% |
PUNE REGION | BARAMATI ZONE | SOLAPUR CIRCLE | BARSI DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 22 | 19 | 15 | 0 | 4 | 1 | 3 | 86% |
PUNE REGION | BARAMATI ZONE | SOLAPUR CIRCLE | BARSI DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 2 | 1 | 28 | 28 | 28 | 28 | 28 | 50% |
PUNE REGION | BARAMATI ZONE | SOLAPUR CIRCLE | PANDHARPUR DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 2763 | 2644 | 159 | 0 | 8 | 0 | 6 | 96% |
PUNE REGION | BARAMATI ZONE | SOLAPUR CIRCLE | PANDHARPUR DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 1025 | 685 | 130 | 0 | 26 | 7 | 18 | 67% |
PUNE REGION | BARAMATI ZONE | SOLAPUR CIRCLE | PANDHARPUR DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 38 | 36 | 22 | 0 | 8 | 6 | 6 | 95% |
PUNE REGION | BARAMATI ZONE | SOLAPUR CIRCLE | PANDHARPUR DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 12 | 7 | 54 | 0 | 13 | 0 | 6 | 58% |
PUNE REGION | BARAMATI ZONE | SOLAPUR CIRCLE | SOLAPUR RURAL DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 3026 | 2924 | 155 | 0 | 11 | 5 | 7 | 97% |
PUNE REGION | BARAMATI ZONE | SOLAPUR CIRCLE | SOLAPUR RURAL DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 1207 | 853 | 126 | 0 | 22 | 5 | 14 | 71% |
PUNE REGION | BARAMATI ZONE | SOLAPUR CIRCLE | SOLAPUR RURAL DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 15 | 13 | 39 | 0 | 13 | 10 | 10 | 87% |
PUNE REGION | BARAMATI ZONE | SOLAPUR CIRCLE | SOLAPUR RURAL DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 6 | 5 | 24 | 2 | 12 | 2 | 14 | 83% |
PUNE REGION | BARAMATI ZONE | SOLAPUR CIRCLE | SOLAPUR URBAN DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Urban | 7 | 2499 | 2432 | 67 | 0 | 5 | 1 | 3 | 97% |
PUNE REGION | BARAMATI ZONE | SOLAPUR CIRCLE | SOLAPUR URBAN DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Urban | 90 | 1263 | 1079 | 87 | 0 | 9 | 5 | 6 | 85% |
PUNE REGION | BARAMATI ZONE | SOLAPUR CIRCLE | SOLAPUR URBAN DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Urban | 7 | 24 | 23 | 12 | 0 | 4 | 1 | 2 | 96% |
PUNE REGION | BARAMATI ZONE | SOLAPUR CIRCLE | SOLAPUR URBAN DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Urban | 90 | 12 | 3 | 32 | 0 | 12 | 0 | 4 | 25% |
PUNE REGION | KOLHAPUR ZONE | KOLHAPUR CIRCLE | GADHINGLAJ DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 1426 | 1362 | 27 | 0 | 5 | 2 | 4 | 96% |
PUNE REGION | KOLHAPUR ZONE | KOLHAPUR CIRCLE | GADHINGLAJ DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 633 | 424 | 116 | 1 | 29 | 4 | 19 | 67% |
PUNE REGION | KOLHAPUR ZONE | KOLHAPUR CIRCLE | GADHINGLAJ DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 24 | 23 | 34 | 0 | 4 | 0 | 2 | 96% |
PUNE REGION | KOLHAPUR ZONE | KOLHAPUR CIRCLE | GADHINGLAJ DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 4 | 4 | 18 | 4 | 14 | 17 | 17 | 100% |
PUNE REGION | KOLHAPUR ZONE | KOLHAPUR CIRCLE | ICHALKARANJI DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 599 | 584 | 14 | 0 | 2 | 1 | 1 | 97% |
PUNE REGION | KOLHAPUR ZONE | KOLHAPUR CIRCLE | ICHALKARANJI DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Urban | 7 | 1058 | 1023 | 26 | 0 | 3 | 1 | 2 | 97% |
PUNE REGION | KOLHAPUR ZONE | KOLHAPUR CIRCLE | ICHALKARANJI DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 71 | 45 | 149 | 0 | 39 | 19 | 42 | 63% |
PUNE REGION | KOLHAPUR ZONE | KOLHAPUR CIRCLE | ICHALKARANJI DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Urban | 90 | 179 | 137 | 99 | 0 | 21 | 2 | 11 | 77% |
PUNE REGION | KOLHAPUR ZONE | KOLHAPUR CIRCLE | ICHALKARANJI DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 8 | 8 | 17 | 1 | 6 | 2 | 4 | 100% |
PUNE REGION | KOLHAPUR ZONE | KOLHAPUR CIRCLE | ICHALKARANJI DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Urban | 7 | 7 | 6 | 4 | 0 | 1 | 0 | 1 | 86% |
PUNE REGION | KOLHAPUR ZONE | KOLHAPUR CIRCLE | ICHALKARANJI DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Urban | 90 | 5 | 5 | 2 | 0 | 0 | 0 | 0 | 100% |
PUNE REGION | KOLHAPUR ZONE | KOLHAPUR CIRCLE | JAYASINGPUR DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 2022 | 1954 | 28 | 0 | 4 | 1 | 3 | 97% |
PUNE REGION | KOLHAPUR ZONE | KOLHAPUR CIRCLE | JAYASINGPUR DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 365 | 250 | 152 | 0 | 30 | 4 | 16 | 68% |
PUNE REGION | KOLHAPUR ZONE | KOLHAPUR CIRCLE | JAYASINGPUR DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 39 | 38 | 13 | 0 | 3 | 0 | 2 | 97% |
PUNE REGION | KOLHAPUR ZONE | KOLHAPUR CIRCLE | JAYASINGPUR DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 2 | 1 | 3 | 3 | 3 | 3 | 3 | 50% |
PUNE REGION | KOLHAPUR ZONE | KOLHAPUR CIRCLE | KOLHAPUR RURAL I DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 2954 | 2865 | 82 | 0 | 4 | 1 | 3 | 97% |
PUNE REGION | KOLHAPUR ZONE | KOLHAPUR CIRCLE | KOLHAPUR RURAL I DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 338 | 190 | 144 | 1 | 49 | 2 | 48 | 56% |
PUNE REGION | KOLHAPUR ZONE | KOLHAPUR CIRCLE | KOLHAPUR RURAL I DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 24 | 22 | 21 | 1 | 4 | 1 | 3 | 92% |
PUNE REGION | KOLHAPUR ZONE | KOLHAPUR CIRCLE | KOLHAPUR RURAL II DIV. | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 3550 | 3437 | 25 | 0 | 3 | 1 | 2 | 97% |
PUNE REGION | KOLHAPUR ZONE | KOLHAPUR CIRCLE | KOLHAPUR RURAL II DIV. | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 715 | 533 | 132 | 0 | 23 | 4 | 11 | 75% |
PUNE REGION | KOLHAPUR ZONE | KOLHAPUR CIRCLE | KOLHAPUR RURAL II DIV. | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 35 | 34 | 23 | 0 | 5 | 1 | 4 | 97% |
PUNE REGION | KOLHAPUR ZONE | KOLHAPUR CIRCLE | KOLHAPUR RURAL II DIV. | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 3 | 2 | 7 | 4 | 6 | 4 | 6 | 67% |
PUNE REGION | KOLHAPUR ZONE | KOLHAPUR CIRCLE | KOLHAPUR URBAN DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Urban | 7 | 2650 | 2584 | 86 | 0 | 3 | 1 | 2 | 98% |
PUNE REGION | KOLHAPUR ZONE | KOLHAPUR CIRCLE | KOLHAPUR URBAN DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Urban | 90 | 184 | 171 | 123 | 0 | 29 | 3 | 9 | 93% |
PUNE REGION | KOLHAPUR ZONE | KOLHAPUR CIRCLE | KOLHAPUR URBAN DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Urban | 7 | 116 | 115 | 12 | 0 | 1 | 0 | 1 | 99% |
PUNE REGION | KOLHAPUR ZONE | KOLHAPUR CIRCLE | KOLHAPUR URBAN DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Urban | 90 | 2 | 0 | 0 | 0 | 0 | 0 | 0 | 0% |
PUNE REGION | KOLHAPUR ZONE | SANGLI CIRCLE | ISLAMPUR DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 1883 | 1834 | 36 | 0 | 5 | 2 | 4 | 97% |
PUNE REGION | KOLHAPUR ZONE | SANGLI CIRCLE | ISLAMPUR DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 138 | 70 | 153 | 1 | 42 | 8 | 19 | 51% |
PUNE REGION | KOLHAPUR ZONE | SANGLI CIRCLE | ISLAMPUR DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 12 | 12 | 13 | 0 | 4 | 0 | 3 | 100% |
PUNE REGION | KOLHAPUR ZONE | SANGLI CIRCLE | ISLAMPUR DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 2 | 2 | 23 | 18 | 21 | 18 | 21 | 100% |
PUNE REGION | KOLHAPUR ZONE | SANGLI CIRCLE | KAVATHEMAHANKAL DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 1641 | 1570 | 121 | 0 | 7 | 3 | 5 | 96% |
PUNE REGION | KOLHAPUR ZONE | SANGLI CIRCLE | KAVATHEMAHANKAL DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 644 | 182 | 160 | 1 | 35 | 25 | 24 | 28% |
PUNE REGION | KOLHAPUR ZONE | SANGLI CIRCLE | KAVATHEMAHANKAL DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 3 | 3 | 25 | 8 | 15 | 8 | 11 | 100% |
PUNE REGION | KOLHAPUR ZONE | SANGLI CIRCLE | KAVATHEMAHANKAL DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 2 | 2 | 75 | 15 | 45 | 15 | 45 | 100% |
PUNE REGION | KOLHAPUR ZONE | SANGLI CIRCLE | SANGLI RURAL DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 1823 | 1730 | 51 | 0 | 5 | 1 | 4 | 95% |
PUNE REGION | KOLHAPUR ZONE | SANGLI CIRCLE | SANGLI RURAL DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 434 | 299 | 133 | 1 | 22 | 2 | 9 | 69% |
PUNE REGION | KOLHAPUR ZONE | SANGLI CIRCLE | SANGLI RURAL DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 8 | 6 | 31 | 0 | 9 | 7 | 7 | 75% |
PUNE REGION | KOLHAPUR ZONE | SANGLI CIRCLE | SANGLI RURAL DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 1 | 1 | 12 | 12 | 12 | 12 | 12 | 100% |
PUNE REGION | KOLHAPUR ZONE | SANGLI CIRCLE | SANGLI URBAN DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Urban | 7 | 1280 | 1232 | 23 | 0 | 3 | 1 | 2 | 96% |
PUNE REGION | KOLHAPUR ZONE | SANGLI CIRCLE | SANGLI URBAN DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Urban | 90 | 1550 | 1392 | 113 | 0 | 14 | 7 | 8 | 90% |
PUNE REGION | KOLHAPUR ZONE | SANGLI CIRCLE | SANGLI URBAN DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Urban | 7 | 51 | 50 | 8 | 0 | 2 | 0 | 1 | 98% |
PUNE REGION | KOLHAPUR ZONE | SANGLI CIRCLE | SANGLI URBAN DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Urban | 90 | 14 | 12 | 4 | 0 | 1 | 0 | 1 | 86% |
PUNE REGION | KOLHAPUR ZONE | SANGLI CIRCLE | VITA DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 2350 | 2291 | 79 | 0 | 6 | 1 | 4 | 97% |
PUNE REGION | KOLHAPUR ZONE | SANGLI CIRCLE | VITA DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 461 | 263 | 151 | 0 | 29 | 7 | 19 | 57% |
PUNE REGION | KOLHAPUR ZONE | SANGLI CIRCLE | VITA DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 49 | 43 | 22 | 0 | 4 | 1 | 2 | 88% |
PUNE REGION | KOLHAPUR ZONE | SANGLI CIRCLE | VITA DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 4 | 2 | 39 | 32 | 36 | 32 | 36 | 50% |
PUNE REGION | PUNE ZONE | GANESHKHIND (U) CIRCLE | BHOSARI DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Metro | 3 | 897 | 897 | 40 | 0 | 6 | 1 | 5 | 100% |
PUNE REGION | PUNE ZONE | GANESHKHIND (U) CIRCLE | BHOSARI DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Metro | 90 | 16734 | 13904 | 140 | 0 | 17 | 1 | 10 | 83% |
PUNE REGION | PUNE ZONE | GANESHKHIND (U) CIRCLE | BHOSARI DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Metro | 3 | 2 | 2 | 7 | 1 | 4 | 1 | 4 | 100% |
PUNE REGION | PUNE ZONE | GANESHKHIND (U) CIRCLE | BHOSARI DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Metro | 90 | 70 | 48 | 115 | 0 | 15 | 0 | 6 | 69% |
PUNE REGION | PUNE ZONE | GANESHKHIND (U) CIRCLE | KOTHRUD DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Metro | 3 | 75 | 75 | 8 | 0 | 3 | 1 | 1 | 100% |
PUNE REGION | PUNE ZONE | GANESHKHIND (U) CIRCLE | KOTHRUD DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Metro | 90 | 3312 | 2878 | 134 | 0 | 17 | 9 | 10 | 87% |
PUNE REGION | PUNE ZONE | GANESHKHIND (U) CIRCLE | KOTHRUD DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Metro | 3 | 23 | 22 | 6 | 0 | 2 | 1 | 1 | 96% |
PUNE REGION | PUNE ZONE | GANESHKHIND (U) CIRCLE | KOTHRUD DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Metro | 90 | 56 | 48 | 53 | 0 | 9 | 0 | 5 | 86% |
PUNE REGION | PUNE ZONE | GANESHKHIND (U) CIRCLE | PIMPRI DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Metro | 3 | 967 | 966 | 148 | 0 | 10 | 2 | 7 | 100% |
PUNE REGION | PUNE ZONE | GANESHKHIND (U) CIRCLE | PIMPRI DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Metro | 90 | 14413 | 11307 | 149 | 0 | 30 | 4 | 23 | 78% |
PUNE REGION | PUNE ZONE | GANESHKHIND (U) CIRCLE | PIMPRI DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Metro | 3 | 2 | 2 | 15 | 13 | 14 | 13 | 14 | 100% |
PUNE REGION | PUNE ZONE | GANESHKHIND (U) CIRCLE | PIMPRI DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Metro | 90 | 49 | 35 | 144 | 0 | 22 | 0 | 4 | 71% |
PUNE REGION | PUNE ZONE | GANESHKHIND (U) CIRCLE | SHIVAJI NAGAR DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Metro | 3 | 187 | 185 | 52 | 0 | 11 | 7 | 7 | 99% |
PUNE REGION | PUNE ZONE | GANESHKHIND (U) CIRCLE | SHIVAJI NAGAR DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Metro | 90 | 6567 | 5686 | 140 | 0 | 17 | 10 | 14 | 87% |
PUNE REGION | PUNE ZONE | GANESHKHIND (U) CIRCLE | SHIVAJI NAGAR DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Metro | 3 | 13 | 13 | 14 | 0 | 3 | 0 | 1 | 100% |
PUNE REGION | PUNE ZONE | GANESHKHIND (U) CIRCLE | SHIVAJI NAGAR DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Metro | 90 | 51 | 40 | 77 | 0 | 12 | 0 | 7 | 78% |
PUNE REGION | PUNE ZONE | PUNE (R) CIRCLE | MANCHAR O&M DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 2620 | 2535 | 110 | 0 | 8 | 2 | 6 | 97% |
PUNE REGION | PUNE ZONE | PUNE (R) CIRCLE | MANCHAR O&M DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 309 | 227 | 153 | 2 | 26 | 4 | 20 | 73% |
PUNE REGION | PUNE ZONE | PUNE (R) CIRCLE | MANCHAR O&M DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 12 | 11 | 19 | 0 | 7 | 0 | 7 | 92% |
PUNE REGION | PUNE ZONE | PUNE (R) CIRCLE | MANCHAR O&M DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 1 | 1 | 60 | 60 | 60 | 60 | 60 | 100% |
PUNE REGION | PUNE ZONE | PUNE (R) CIRCLE | PUNE DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 15616 | 15121 | 104 | 0 | 9 | 2 | 6 | 97% |
PUNE REGION | PUNE ZONE | PUNE (R) CIRCLE | PUNE DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 588 | 472 | 116 | 0 | 19 | 5 | 12 | 80% |
PUNE REGION | PUNE ZONE | PUNE (R) CIRCLE | PUNE DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 31 | 29 | 41 | 0 | 9 | 1 | 7 | 94% |
PUNE REGION | PUNE ZONE | PUNE (R) CIRCLE | PUNE DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 9 | 7 | 141 | 8 | 31 | 10 | 10 | 78% |
PUNE REGION | PUNE ZONE | PUNE (R) CIRCLE | RAJGURUNAGAR DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Rural | 15 | 3325 | 3257 | 133 | 0 | 9 | 0 | 7 | 98% |
PUNE REGION | PUNE ZONE | PUNE (R) CIRCLE | RAJGURUNAGAR DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Rural | 90 | 7810 | 7451 | 158 | 0 | 13 | 7 | 9 | 95% |
PUNE REGION | PUNE ZONE | PUNE (R) CIRCLE | RAJGURUNAGAR DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Rural | 15 | 23 | 21 | 12 | 0 | 3 | 0 | 1 | 91% |
PUNE REGION | PUNE ZONE | PUNE (R) CIRCLE | RAJGURUNAGAR DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Rural | 90 | 54 | 48 | 112 | 0 | 10 | 0 | 2 | 89% |
PUNE REGION | PUNE ZONE | RASTAPETH (U) CIRCLE | BUNDGARDEN DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Metro | 3 | 2429 | 2425 | 41 | 0 | 6 | 2 | 5 | 100% |
PUNE REGION | PUNE ZONE | RASTAPETH (U) CIRCLE | BUNDGARDEN DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Metro | 90 | 7632 | 6424 | 114 | 0 | 13 | 9 | 10 | 84% |
PUNE REGION | PUNE ZONE | RASTAPETH (U) CIRCLE | BUNDGARDEN DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Metro | 3 | 5 | 5 | 6 | 0 | 2 | 0 | 2 | 100% |
PUNE REGION | PUNE ZONE | RASTAPETH (U) CIRCLE | BUNDGARDEN DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Metro | 90 | 24 | 21 | 33 | 0 | 9 | 0 | 7 | 88% |
PUNE REGION | PUNE ZONE | RASTAPETH (U) CIRCLE | NAGAR DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Metro | 3 | 1037 | 1030 | 26 | 0 | 3 | 2 | 2 | 99% |
PUNE REGION | PUNE ZONE | RASTAPETH (U) CIRCLE | NAGAR DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Metro | 90 | 5530 | 5117 | 89 | 0 | 13 | 1 | 8 | 93% |
PUNE REGION | PUNE ZONE | RASTAPETH (U) CIRCLE | NAGAR DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Metro | 3 | 13 | 12 | 15 | 0 | 3 | 0 | 1 | 92% |
PUNE REGION | PUNE ZONE | RASTAPETH (U) CIRCLE | NAGAR DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Metro | 90 | 27 | 21 | 77 | 0 | 12 | 0 | 3 | 78% |
PUNE REGION | PUNE ZONE | RASTAPETH (U) CIRCLE | PADMAVATI DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Metro | 3 | 2267 | 2167 | 57 | 0 | 4 | 1 | 2 | 96% |
PUNE REGION | PUNE ZONE | RASTAPETH (U) CIRCLE | PADMAVATI DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Metro | 90 | 3770 | 3529 | 115 | 0 | 7 | 2 | 4 | 94% |
PUNE REGION | PUNE ZONE | RASTAPETH (U) CIRCLE | PADMAVATI DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Metro | 3 | 13 | 9 | 35 | 0 | 7 | 1 | 1 | 69% |
PUNE REGION | PUNE ZONE | RASTAPETH (U) CIRCLE | PADMAVATI DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Metro | 90 | 20 | 15 | 72 | 0 | 14 | 3 | 13 | 75% |
PUNE REGION | PUNE ZONE | RASTAPETH (U) CIRCLE | PARVATI DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Metro | 3 | 438 | 438 | 16 | 0 | 8 | 9 | 8 | 100% |
PUNE REGION | PUNE ZONE | RASTAPETH (U) CIRCLE | PARVATI DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Metro | 90 | 5687 | 4178 | 122 | 0 | 15 | 6 | 11 | 73% |
PUNE REGION | PUNE ZONE | RASTAPETH (U) CIRCLE | PARVATI DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Metro | 3 | 1 | 1 | 3 | 3 | 3 | 3 | 3 | 100% |
PUNE REGION | PUNE ZONE | RASTAPETH (U) CIRCLE | PARVATI DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Metro | 90 | 55 | 50 | 31 | 0 | 8 | 1 | 2 | 91% |
PUNE REGION | PUNE ZONE | RASTAPETH (U) CIRCLE | RASTAPETH DIVISION | Obtaining Electricity Connection-Permanent | INFRA NOT REQUIRED | Metro | 3 | 282 | 279 | 37 | 0 | 5 | 1 | 3 | 99% |
PUNE REGION | PUNE ZONE | RASTAPETH (U) CIRCLE | RASTAPETH DIVISION | Obtaining Electricity Connection-Permanent | INFRA REQUIRED | Metro | 90 | 3262 | 2765 | 140 | 0 | 16 | 11 | 11 | 85% |
PUNE REGION | PUNE ZONE | RASTAPETH (U) CIRCLE | RASTAPETH DIVISION | Obtaining Electricity Connection-Temporary | INFRA NOT REQUIRED | Metro | 3 | 14 | 14 | 4 | 0 | 1 | 1 | 1 | 100% |
PUNE REGION | PUNE ZONE | RASTAPETH (U) CIRCLE | RASTAPETH DIVISION | Obtaining Electricity Connection-Temporary | INFRA REQUIRED | Metro | 90 | 24 | 19 | 107 | 0 | 11 | 2 | 3 | 79% |